Dear congregation,

after our building application was approved by the municipal council, it was submitted to the responsible district office (in Bavaria) on 24.08. They informed us that our building application is subject to the approval fiction. A prerequisite for this is that the documents are complete and verifiable.
On 07.09. we then received a notice that our application was not complete or verifiable. Six points were listed that needed to be resubmitted. We had these revised and submitted the supplements again. Today I reached the technical examiner at the building authority. She informed me that all requirements have now been met. Our architect also had contact with her and informed us today that our building application would now "go to the meeting."
Unfortunately, that tells me little and I won’t reach our architect again until the beginning of the week.

I now have three pressing questions:
1. Can you help me understand what is meant by "go to the meeting"? I had assumed that the building application would first be technically and then more thoroughly examined.
2. What are the next steps?
3. How long do you estimate the building permit will still take?

Thank you in advance! :)
 

Tarnari

2021-10-07 20:43:53
  • #2
I cannot answer your questions. I can only say that applications are processed slowly or quickly depending on the region. With us (Rheinland), 6 months were expected. It took 10 because of a tree.
 

majuhenema

2021-10-07 21:13:46
  • #3
Thank you for your answer! If I understand correctly, in Bavaria, due to the "Genehmigungsfiktion," a building application is considered automatically approved if we do not hear anything from the building authority three months after the notification of examinability and completeness. Therefore, I hope that after the verbal approval, we will now also receive this in writing and that the three months will start from then. What do the others say?
 

MaxiFrett

2021-10-07 21:52:06
  • #4
In our region - Niedersachsen - it was such that after the documents were additionally requested by the wastewater authority and everything was complete, the processor handled and approved the application within 3 days after his vacation. He also prioritized it upon a friendly inquiry. Actually, it was not his turn according to the order.
 

11ant

2021-10-07 22:11:02
  • #5
That sounds to me as if your building application is to be submitted to the municipal council or its building committee (which of course only happens once all documents have been fully submitted and it is formally correct). I interpret this accordingly as a good sign for a desired course.
 

majuhenema

2021-10-07 22:29:12
  • #6


Thank you for your answer! That's exactly how I understand it as well. I thought the course of our village building application looks as follows (to put it simply): Application submission -> Municipality reviews it, has no objections -> Municipal council approves it -> Municipality/mayor forwards it to the district building authority -> Technical check for completeness/checkability -> Now the "actual" examination takes place.

We are at the penultimate step. I just can’t explain what is meant by the statement "the building application can now go into the meeting." Does the district building authority also have a meeting where such matters are decided? In the municipal council of our village, the application has been approved since mid-August...
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
29.10.2013Property reserved, construction financing plan, architect/building permit application21
17.12.2014Building application "deferred". What does that mean?19
28.02.2015Building application submitted/open detailed questions/looking forward to suggestions39
15.06.2015Garage - Building Application - Confusion36
30.10.2015Can the building application be submitted this year?14
01.02.2017Building application is becoming increasingly complicated!20
27.04.2017Carport deviation from the building application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?44
20.11.2020Wait with the building application because of the child construction allowance1354
04.05.2020Duties of a carport manufacturer23
30.11.2020Building Authority Problems - Purchased a Defective Plot56
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
30.01.2021The building authority rejects the building application because the house is planned too far back86
09.05.2022Building application due to parking spaces not approved. What can happen?30
03.03.2023Building permit application without height survey?15
10.03.2023Preliminary building approval positive, building application criticized position29
24.11.2024Building authority requires open space design plan for single-family house - experiences?37

Oben