majuhenema
2021-10-07 20:24:30
- #1
Dear congregation,
after our building application was approved by the municipal council, it was submitted to the responsible district office (in Bavaria) on 24.08. They informed us that our building application is subject to the approval fiction. A prerequisite for this is that the documents are complete and verifiable.
On 07.09. we then received a notice that our application was not complete or verifiable. Six points were listed that needed to be resubmitted. We had these revised and submitted the supplements again. Today I reached the technical examiner at the building authority. She informed me that all requirements have now been met. Our architect also had contact with her and informed us today that our building application would now "go to the meeting."
Unfortunately, that tells me little and I won’t reach our architect again until the beginning of the week.
I now have three pressing questions:
1. Can you help me understand what is meant by "go to the meeting"? I had assumed that the building application would first be technically and then more thoroughly examined.
2. What are the next steps?
3. How long do you estimate the building permit will still take?
Thank you in advance! :)
after our building application was approved by the municipal council, it was submitted to the responsible district office (in Bavaria) on 24.08. They informed us that our building application is subject to the approval fiction. A prerequisite for this is that the documents are complete and verifiable.
On 07.09. we then received a notice that our application was not complete or verifiable. Six points were listed that needed to be resubmitted. We had these revised and submitted the supplements again. Today I reached the technical examiner at the building authority. She informed me that all requirements have now been met. Our architect also had contact with her and informed us today that our building application would now "go to the meeting."
Unfortunately, that tells me little and I won’t reach our architect again until the beginning of the week.
I now have three pressing questions:
1. Can you help me understand what is meant by "go to the meeting"? I had assumed that the building application would first be technically and then more thoroughly examined.
2. What are the next steps?
3. How long do you estimate the building permit will still take?