Iulius
2015-07-30 18:11:59
- #1
Hello,
a case example:
the construction company ordered too little concrete and only after 13 hours poured the last third of a floor slab.
Weather: 10-15 degrees and rain.
Is this still acceptable or are late effects to be expected?
Thank you and best regards
a case example:
the construction company ordered too little concrete and only after 13 hours poured the last third of a floor slab.
Weather: 10-15 degrees and rain.
Is this still acceptable or are late effects to be expected?
Thank you and best regards