Assessment of soil report - Should additional costs be planned?

  • Erstellt am 2021-07-11 10:20:40

K1300S

2021-07-11 16:09:01
  • #1
Then he says "yes," but you don't know how expensive it will be. Removing topsoil doesn't cost much anyway. A few euros per m², that's it.
 

Andre77

2021-07-11 16:21:58
  • #2
Basically correct. But you initially have a reference point. If he says that it matches what the GU demands for the included earthworks. At least the specifications were in my construction performance description and I was then somewhat more reassured.
 

Matthias_1212

2021-07-11 20:57:48
  • #3
Thank you very much. I have just written to the reviewer and asked for his assessment. But it is certainly reassuring that the [Gutachten] regarding the soil condition does not deviate significantly from the “standard.”
 