Additional floor... Liability insurance for damages?

  • Erstellt am 2019-07-19 15:28:22

Evamaria

2019-07-19 15:28:22
  • #1
Hello everyone! I am currently building an additional floor as a residential unit on my parents' house. The construction management is done by the architect. Construction began in February. Although it was raining heavily at that time and we expressed concerns about starting construction, the shell construction still began. The house has 6 units, that is the ground floor, 1st and 2nd upper floors. When the roof opening for the staircase was made, standing and dirty water ran from the roof down all the walls to the ground floor. A complete renovation of the staircase is now necessary. My question: shouldn't precautions have been taken before the roof opening to prevent the entire staircase from being affected? The floor below... okay, but all three floors? Also, the open roof was not protected against rain and in two apartments on the 2nd upper floor water penetrated and the tenants demand removal of the water stains. Whose liability insurance covers this? Regards Evamaria
 

Tassimat

2019-07-19 15:37:12
  • #2
Is there anything contractual about how the still inhabited units are to be protected from the construction? Have you noted the concerns in writing?

I’m afraid you have to first repair the water stains and the stairwell at your own expense and then try to sue for reimbursement. But if there is nothing in writing regarding covering the stairwell, I don’t see how you’d get any money back.
 

Evamaria

2019-07-19 15:44:41
  • #3
I feared so. Thanks for the information
 

Evamaria

2019-07-19 15:46:42
  • #4
No, there is nothing contractual and we have only expressed the concerns verbally. I feared that the costs would be borne by us. Thank you for the info!
 

11ant

2019-07-19 16:21:54
  • #5
But at least in front of witnesses, I hope. So a coordinating authority "above" the involved craftsmen, the scaffolder, etc. There should be something like "good faith" in "recognized rules of technology" to hold the architect’s professional liability insurance accountable. Professionally, he must have been aware of the temporary vulnerability the measures would cause for the existing building. A lawyer experienced in construction contract law should find ways to hold the expert liable for his negligence. After all, you didn’t do this for fun with Karljosef's brother-in-law's buddy, but with an expert. So I don’t think you have to explicitly explain in writing to an architect what a roof can do only while it exists, and that rain is wet and typically comes from above.
 

HilfeHilfe

2019-07-19 17:06:18
  • #6
Only legal recourse. Is the damage very severe? Is it worth suing or can the craftsmen manage it?
 

Similar topics
23.10.2008We need an architect - or should I do it myself?14
02.01.2009Experiences with architects15
19.03.2013Turnkey or build with architects?19
21.07.2013Cost estimates from two architects differ greatly!10
13.11.2013Do you absolutely need an architect?10
16.12.2013Pre-planning with the architect - is having your own floor plan sensible?18
30.01.2014Architect's cost estimation15
07.04.2014Bring light into the stairwell?10
21.08.2014Construction costs when building with architects. What does your experience say?18
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
19.12.2014Finding architects - but how?26
30.04.2015Floor plan single-family house approx. 140m² - separable staircase35
08.09.2015Massive house by the architect, approximate costs?16
23.09.2015Responsibilities of the Architect in Tendering18
29.10.2015Is it normal for the purchase of land to be tied to an architect?16
19.01.2016Construction project with architects31
20.08.2016Should the house be planned by a general contractor or architects?30
10.03.2017Payment of the architect16
12.10.2017Cost of enclosed space. First draft discussed with architects27
03.07.2022Roll plaster in the stairwell - how to apply?20

Oben