Additional costs in a general contractor contract

  • Erstellt am 2009-08-31 17:44:53

stanger

2009-08-31 17:44:53
  • #1
Hello
we have a general contractor contract with a fixed house price. Then the additional house costs are added. These are listed separately. Now we already have an overrun of more than 50% of these budgeted house costs in the position permits. Likewise, we now also have again an overrun of about 17% in the master builder work, which we should now sign contractually.
How does this look legally?
Thanks for the feedback.
stanger
 

6Richtige

2009-09-01 11:18:32
  • #2
Hello stanger,

what exactly does fixed house price mean? What applies is what you signed, it is best if you put the corresponding passage here, then more can be said. If extreme cost increases threaten even before the start of construction, without you having redesigned or changed the house, it was probably the cheapest provider commissioned, who now wants to recoup his profits in this way, or according to which criteria did you select this provider?
 

stanger

2009-09-01 11:36:46
  • #3
We have a work contract with a fixed flat rate for the building. Then the usual additional costs are listed, which are estimated in the brackets: 1. preparatory work, 2b) additional building costs (heating costs during the construction phase, construction electricity, installation of LS basement, etc.), then 4. surroundings and 5. ancillary construction costs.
Under the ancillary construction costs, the building permit costs were over 50% higher than budgeted. And for the first two items of the master builder’s work for the surroundings, the costs are now again 17% more expensive than budgeted. These are several thousand francs, and we are already well over budget.
We are pretty stuck now.
Thank you.
 

6Richtige

2009-09-01 12:34:15
  • #4
Hello stanger,

Often the lump sum price is also referred to as a fixed price, but this regularly leads to misconceptions. The lump sum price is, in the absence of other agreements, a "fixed price" only in the sense that it is not changed by external circumstances such as inflation, wage increases, or material price increases. However, it is quite possible to agree on price escalation clauses for such circumstances in a lump sum contract, which then makes the lump sum price a "sliding price." The assumption that a lump sum price is a fixed price in the sense that all changes or additional wishes of the builder are already covered by the lump sum price is wrong. Such a "fixed price" does not exist. Therefore, the final total price can easily be 30% above the original lump sum price even in a lump sum agreement.

Since the price increases you describe result from only estimated ancillary costs (with an estimate one can easily be off by 100%, as long as the total price for the house looks nice and low on paper ;)) you will not be able to do much about it.

Since you live in Switzerland, you should ask this question again for safety in the Swiss forum.

If you answer my question about your selection criteria for your general contractor, perhaps other builders can still learn something and avoid costly mistakes.
 

stanger

2009-09-01 12:37:32
  • #5
Hello thank you very much for your explanations. This is a severe disappointment for us and we will certainly face greater financial problems as a result. We do not yet know what other "over budget" costs will arise from the further work. :mad: Thank you and regards
 

Similar topics
20.07.2011House construction: Equity / incidental construction costs realistic?14
16.07.2012The builder "outsources" fixed-price services to subcontractors12
18.10.2012Ancillary construction costs and general expenses for a new semi-detached house14
18.06.2013Too few incidental construction costs or is the cost breakdown okay?16
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
13.03.2014Additional construction costs and realistic additional construction costs?21
11.10.2022List of incidental construction costs. More expensive "on the builder's side"?154
19.08.2014Home construction financing - House price and ancillary construction costs27
26.04.2016Estimation of construction costs (and ancillary construction costs)11
23.06.2016Additional construction costs ... but which ones?39
16.10.2016Construction ancillary costs not visible?14
14.12.2016House planning, offer, financing, fixed price19
24.06.2017Construction ancillary costs: Bank requires signature from the architect16
18.05.2018Construction costs for a single-family house, additional building costs?24
18.10.2020Baunebenkosten calculation realistic?94
13.10.2020Land available - ancillary construction costs, ancillary house costs, financing?34
10.12.2020Assessment of Additional Construction Costs - Have I considered everything?34
14.01.2021URGENT: Plausibility Check of Additional Construction Costs - 2 Days Before Deadline43
06.02.2022Are additional construction costs realistic? - 175m² living area KfW 5515
17.12.2024Is a house including ancillary construction costs feasible for 380K EUR?28

Oben