Acknowledgment of receipt for our building application from the building authority Deadlines in Saxony

  • Erstellt am 2019-05-14 14:53:37

Sternchen49

2019-05-14 14:53:37
  • #1
Hello,
I have a question for you. Does anyone know if there is a deadline by which the building authority must check the application for completeness?
Thank you.
 

Andre77

2019-05-14 21:30:32
  • #2
Within 14 days, an acknowledgment of receipt was sent with the information on what was missing, or what, and a deadline by which the additional requests should be received.
 

Sternchen49

2019-05-20 09:54:46
  • #3
We only received mail after 7 weeks, with the notification that documents were missing.
 

Andre77

2019-05-20 10:22:10
  • #4
To summarize my case:

On April 12th, the application arrived by mail at the building authority.
Pretty much exactly 12 days later, the acknowledgment of receipt came with information about what was missing. I collected this and resubmitted it by mail a few days later, including the neighbors' signatures.
A few days later, I was already able to see in the municipality's council information system that my project will be on the agenda tomorrow. However, it was already visible as approved in the public system.

So it seems to be just a formality now that the building permit will be granted to me. The water engineering company (drinking water) commissioned by the municipality has already contacted me, and the discharge permit also arrived at the end of last week.

Therefore, I can say that the processing here took about 4-5 weeks.
 

Sternchen49

2019-05-20 11:46:24
  • #5
I'm happy for you, Andre77.
 

Similar topics
15.02.2011Building permit application12
28.12.2013Conversion of agricultural land to building plot, objection, building authority, building regulations12
28.06.2015Knee wall height / Proposal from the building authority33
20.06.2016Building Authority Approval10
11.04.2017Building authority wants site inspection116
04.07.2017Problems with the building authority due to soil slips and retaining walls!27
13.07.2017Do you need the building approval from the building authority?15
07.11.2017What questions should be asked to the building authority?19
02.09.2019Problems with neighbor's encroachment and building authority11
30.11.2020Building Authority Problems - Purchased a Defective Plot56
30.01.2021The building authority rejects the building application because the house is planned too far back86
30.12.2020Current processing time for construction financing applications at banks69
03.12.2024Wibank Hessen Loan Application Documents and Experiences55
19.07.2024Application KfW 442 Solar Power for Electric Cars42
05.08.2024No information from the building authority to the property owner58
24.11.2024Building authority requires open space design plan for single-family house - experiences?37

Oben