According to the law, the building permit is automatically granted if

  • Erstellt am 2018-01-08 10:40:34

Klaus1212

2018-01-08 10:40:34
  • #1
Good day,

has anyone also had a bad experience with the Bauamt Hamburg Wandsbek?
The objection period for the building permit expired three weeks ago, and no one at the authority can be reached by phone or in writing.

According to the law, the building permit is automatically granted if the authority does not respond within the deadline.

Could someone possibly help with what can be done now?

Thank you very much.
 

Lumpi_LE

2018-01-08 11:49:36
  • #2
As you write, once you have the official [Eingangsschreiben] + deadline, you can start building. I would just stop by, it's nothing new that authorities only answer the phone at certain times.
 

Steven

2018-01-08 13:58:48
  • #3


Hello Klaus1212

how am I supposed to understand that? Something like this: The authority has granted you the building permit and no one filed an objection? Then you can build.
Or like this: You have applied for the building permit and the authority has not yet responded? There are no mandatory deadlines, only target deadlines.

Steven
 

Alex85

2018-01-08 20:15:03
  • #4


In Hamburg, the processing time for simplified building permit procedures is limited to one or two months depending on the building. If the authority does not make a decision by then, the application is considered approved (approval fiction).

In NRW there is something similar, the exemption procedure. This also has a one-month deadline. If the authority remains silent for one month from the receipt of the documents, the matter is settled. However, the exemption procedure does not end with a building permit, but simply with the waiver of a building permit procedure. Then a week is needed for the construction start notification, the neighbors are informed about the construction project in parallel, and then construction can begin.
 

Steven

2018-01-08 21:04:04
  • #5
Hello Alex85

this is completely new to me. So far, I have only read that a building permit SHOULD be decided within 6 weeks. But nobody cares about that. I am not aware of any automatic building permit after the deadline expires.
Can you tell me where I can read about that?

Steven
 

Lumpi_LE

2018-01-08 21:07:47
  • #6
In the corresponding building regulations, it is the same in Saxony, deadline 3 months.
 

Similar topics
31.10.2008Is a building permit also required for a carport and equipment shed?13
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
28.11.2024Neighbor's lawsuit against approved building permit46
16.01.2017No building permit as long as the land is not developed?10
20.08.2017Issuance of the building permit?24
21.06.2018What must be included in the building permit? Legal certainty?19
18.09.2018Immission protection concerns self-service gas station - building permit?20
24.10.2018Broker sells house without current building permit. Notary costs?25
28.08.2019Building permit for terrace roofing14
04.11.2019Is only part of the building permit enforceable? How long is the building permit valid?42
10.01.2020Construction loan without building permit possible?17
23.09.2020Child construction allowance with non-final building permit49
30.07.2021Is building without a building permit possible?26
17.11.2021Official liability building permit neighbor - keywords sought14
28.06.2024Building permit - is a lawyer useful?12

Oben