Hello,
what came first? The chicken or the egg?
How is the following topic usually solved in construction?
I have pre-wall elements that I install with drywall. According to the energy consultant, the base plaster must be applied to the walls beforehand so that we don’t run into problems later during the blower door test.
So, if I have the plasterers come, they plaster everything for me, but if I then have rough-in installations for water etc., they must be installed beforehand, before the plasterers come.
Does the plumbing company usually come in several stages? Do they prepare the piping first and then later the pre-wall elements?
What is usual? Thanks, regards
what came first? The chicken or the egg?
How is the following topic usually solved in construction?
I have pre-wall elements that I install with drywall. According to the energy consultant, the base plaster must be applied to the walls beforehand so that we don’t run into problems later during the blower door test.
So, if I have the plasterers come, they plaster everything for me, but if I then have rough-in installations for water etc., they must be installed beforehand, before the plasterers come.
Does the plumbing company usually come in several stages? Do they prepare the piping first and then later the pre-wall elements?
What is usual? Thanks, regards