Trouble with the developer - Taking special equipment in the construction contract

  • Erstellt am 2012-06-10 11:15:47

Bauexperte

2012-06-10 11:15:47
  • #1
Hello Bernd,

I am not allowed to provide legal advice; this is reserved exclusively for the consulting professions in Germany!


This incident is a good example that you - sorry - saved in the wrong place beforehand...

In your contract for work - in § xyz concerning remuneration - it certainly says something like: "If services agreed upon in § xyz are removed, the refund offered by the contractor for the service applies, with which the client expressly agrees."

With that, you are the last one and have no means to oppose the offered amount of refund. A review of the contract for work including attachments by competent parties beforehand would have demanded this formulation for specification.

In my opinion, § 649 of the Building Code has less to do with it, since you do not want to entirely terminate the contract for work but only reduce it by a certain service.

Best regards
 

posterino

2012-06-10 11:36:24
  • #2
Hello construction expert,
thank you very much for your quick response.

I just looked through the contract again and found the following regarding termination:
The client's right of termination is governed by § 649 of the Construction Code. The contractor's right of termination is governed by §§ 642, 643 of the Construction Code.
Further explanations regarding termination are not included in the contract.
Does this not mean that in this case, even if not the entire contract but only one position is terminated, § 649 still applies?
Would the calculation of what the builder can withhold then not be: 5% of the contract value + his incurred costs, whereby he would still have to credibly prove these?

We previously had an identical case where our builder played the same trick:
Position according to the construction contract 680.00 euros; refund without giving reasons only with reference to § 649 Construction Code and that this was his right 120.00 euros.

Thank you again for your non-binding opinion without legal advice.

Regards
Bernd
 

Bauexperte

2012-06-10 13:52:06
  • #3
Hello,


Again, I am not a lawyer, so I must not provide legal advice and therefore my answer is based solely on my subjective experience.

For me, a change in service has nothing to do with the termination of the contract; not even when a partial service is removed. The relevant section in the Building Code is actually very clear.

Take a look at the remuneration section of your contract, in my opinion you should find what you are looking for there; if not, the only help is advice from a lawyer specializing in construction law, if no mutual agreement can be reached otherwise.
Since your private message to me is identical, no further response from me is needed.

Kind regards
 

posterino

2012-06-10 13:56:43
  • #4
Hello construction expert,

thank you very much for your opinion!

Greetings and have a nice Sunday...
Bernd
 

Alchemist40

2012-06-11 21:05:16
  • #5
Hello everyone! I am also not part of the consulting profession, but I can look it up in the Building Code. The relevant paragraph reads:
§ 649 Right of termination of the client
"The client may terminate the contract at any time until the completion of the work. If the client terminates, the contractor is entitled to demand the agreed remuneration; however, he must credit what he saves in expenses due to the termination of the contract or what he earns or maliciously fails to earn by using his labor elsewhere. It is presumed that the contractor is entitled to 5 percent of the agreed remuneration attributable to the part of the work not yet performed." The Building Code therefore assumes remuneration of 5%. If I were you, I would demand proof from the developer that the significantly higher costs he is claiming have actually been incurred.
 

Hilaria

2012-07-05 09:24:45
  • #6


Hello Bauexperte, stupid question, who reviews such a contract for work and services competently?

Thanks.
 

Similar topics
05.03.2020House contract signed40
23.03.2011Developer or architect?15
18.02.2014Massive problems with the builder - is contract termination possible?33
28.04.2014Cost estimate - contract for work16
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
07.05.2015Have the work contract checked by a professional37
06.07.2015Termination of work contract for house construction (before construction)14
22.09.2015Building Code - Developer Contract - Postponement of Contractual Handover Date14
06.12.2016Contract for work before property purchase - real estate acquisition tax?10
22.02.2016Signature of the work contract before financing?15
04.07.2016Purchase of property under a work contract12
19.07.2016When did you sign the work contract? Prior planning?12
05.09.2017Developer or general contractor! Safety?30
08.08.2018Withdrawal from the work contract within the withdrawal period23
26.09.2019ScanHaus Work Contract Additional Agreement14
14.04.2020Security deposit according to §650 of the Building Code20
27.01.2020How do I get out of a contract for work?11
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
07.05.2022Work contract with exclusion §14/1522
25.12.2023Behavior in case of imminent delay by the property developer48

Oben