Timing Interior Plaster / Screed / Exterior Plaster - Topic Moisture

  • Erstellt am 2018-05-29 14:15:32

cybergnom

2018-05-29 14:15:32
  • #1
Hello everyone,

I am currently planning the further construction process of our single-family house.
Now I am facing a "timing problem":
My plasterer (doing interior plaster, exterior plaster, and screed) says that after applying the interior plaster and screed, the building should be allowed to dry for 2-3 months before the exterior plaster is applied. It is possible to do it more or less simultaneously, but he explicitly does not recommend this.
Our installer says that this is not necessary and usually interior and exterior plaster are done more or less at the same time.

The problem:
The installer will only start with his rough installation (duration approx. 3-4 weeks) once the windows are installed (which will be the case in about 4 weeks). Then the mason could finish his facing walls by the beginning of August. However, the plasterer has 3 weeks of company vacation and could only start the interior plaster at the end of August. With 2 months drying time, we would then be at November for the exterior plaster, which according to the plasterer is already critical because of the weather. If the schedule goes like this, we probably won’t finish this year anymore.

Now the question arises whether such a long drying period between interior plaster/screed and exterior plaster is really necessary.

Additional information: Solid construction (36 cm exterior walls), during the shell construction (completion about 2 weeks ago including roof) it only rained very shortly once, the building is situated slightly elevated, there is always wind, so the building is quite dry.

What are the experiences regarding this?
 

Nordlys

2018-05-29 14:24:46
  • #2
At the same time it goes, only inside especially at the ring beam it then dries for a long time. The stone absorbs water on both sides, it has to dry out again.
 

Maria16

2018-05-29 15:14:01
  • #3
We also had the plastering done quite close together. The question of whether to let it dry was indeed raised, but the plasterer saw no problem.

The positive thing was: the scaffolding simply stayed up longer, the standby costs were cheaper than dismantling it and having it rebuilt weeks later. By the way, the exterior plaster took about 3 weeks for us, due to the necessary drying times before the next layer could be applied. This should be taken into account if house connections still need to be made under the scaffolding (especially for heating the screed), because our utilities didn’t do any digging until the scaffolding was removed.
 

Lumpi_LE

2018-05-31 11:50:41
  • #4
Exterior plaster is not needed for moving in. I would have it plastered in the spring and that’s that.
 

Similar topics
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
08.05.2014Most moisture from screed?25
09.10.2014What when in house construction?17
22.04.2015Window, roller shutter, exterior plaster10
10.05.2015Screed uneven - defect removal refused52
10.08.2015In which season of the year is it best to bring screed into the basement10
28.04.2016Order screed - plaster14
18.05.2020Proper Ventilation/Drying of Interior Plaster / Drying Time21
17.11.2016Are venetian blinds legally considered part of the exterior plaster?11
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
09.01.2017Interior and exterior plaster in winter10
09.11.2019Sound problem: Does noise come through masonry - through the exterior plaster?20
09.08.2017Is exterior plastering possible before interior plastering in summer?10
07.10.2018Styrofoam under screed and underfloor heating - What is the name of the product?12
10.03.2019Garage 8m x 7.5m gable roof, strip foundation, exterior plaster costs10
25.10.2020Main connection box installed before interior plaster in the utility room20
21.01.2021Exterior plaster is uneven, window sills are too short, tightness of the ETICS (External Thermal Insulation Composite System)63
31.03.2022Bright lines on fresh interior plaster - future cracks?27
28.07.2023Screed has been in for three days and is still wet?52
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17

Oben