Pädda
2020-10-26 07:43:27
- #1
Hello. Our construction contractor said that the screed would be installed now. After 3 days, tiles are supposed to be laid on the still wet screed in the areas where [Technik] is located. This would allow the heating engineer and the electrician to continue working and to install the gas heating, hot water tank, and controlled residential ventilation. So far, the tilers have advised against this. One said it was not necessary, as it was only about the early start of the screed drying program and for this the gas heating (wall-mounted) is sufficient. The 300L hot water tank can be placed on the floor later, after the screed drying program has finished. The tiler's primary concern is the tile laying pattern, since we will have the same tiles in the utility room as in the kitchen, living room, dining area, and hallway. Do you have an opinion on this?