tumaa
2020-03-04 22:17:39
- #1
Hello everyone,
Today the plasterer came for an inspection.
He looked at the roller shutter boxes and said that 1-2cm are missing so that it is flush with the masonry and that the window installer had to do this.
This now needs to be compensated.
He called a site manager who confirmed it.
I then called the window installer and reported this.
He said: someone has to pay for it, no matter who has to do it.
I: I don’t see why, if it’s your task.
He: we will find a solution, I will consult with another site manager to see how it is legally regulated.
He is currently still on vacation, the call had to be quick. He wanted to get back to me in a few days.
Is that really the case? (there is nothing about this in the window offer.)
Today the plasterer came for an inspection.
He looked at the roller shutter boxes and said that 1-2cm are missing so that it is flush with the masonry and that the window installer had to do this.
This now needs to be compensated.
He called a site manager who confirmed it.
I then called the window installer and reported this.
He said: someone has to pay for it, no matter who has to do it.
I: I don’t see why, if it’s your task.
He: we will find a solution, I will consult with another site manager to see how it is legally regulated.
He is currently still on vacation, the call had to be quick. He wanted to get back to me in a few days.
Is that really the case? (there is nothing about this in the window offer.)