NordischJung
2021-09-11 08:59:24
- #1
Hello everyone,
first of all: for our construction project, we have to build a retaining wall next to the neighbors.
When awarding the contract to the structural engineer, this was completely known and discussed. He then almost tripled the costs for the structural analysis with reference to a "complex and difficult construction project." That was in May of this year. He received the requested soil survey in June and hasn't done anything since then. In the offer, he writes that he will, among other things, calculate/confirm the structural stability (not specified in detail).
Now – at the end of August, it is said -> The retaining wall must be confirmed by a separate geological structural stability report, which he cannot provide. The retaining wall means that we can found on a normal single-family house foundation.
Timewise, we wanted to start 2 months ago. Without informing us, he contacted the soil surveyor in the background, left us in the dark regarding timing, and forwarded all documents without our consent. In fact, he forced an order on us. At this point, I will set aside the violation of the data protection law.
Now we have to pay an extra 2-3k€ and have a 2-month delay in the start of construction because of him and his dawdling.
Is it correct that a structural engineer cannot provide this report? Can I increase the costs in advance because of this and then have the work left undone? Who bears the additional costs? Has anyone ever had a similar case?
first of all: for our construction project, we have to build a retaining wall next to the neighbors.
When awarding the contract to the structural engineer, this was completely known and discussed. He then almost tripled the costs for the structural analysis with reference to a "complex and difficult construction project." That was in May of this year. He received the requested soil survey in June and hasn't done anything since then. In the offer, he writes that he will, among other things, calculate/confirm the structural stability (not specified in detail).
Now – at the end of August, it is said -> The retaining wall must be confirmed by a separate geological structural stability report, which he cannot provide. The retaining wall means that we can found on a normal single-family house foundation.
Timewise, we wanted to start 2 months ago. Without informing us, he contacted the soil surveyor in the background, left us in the dark regarding timing, and forwarded all documents without our consent. In fact, he forced an order on us. At this point, I will set aside the violation of the data protection law.
Now we have to pay an extra 2-3k€ and have a 2-month delay in the start of construction because of him and his dawdling.
Is it correct that a structural engineer cannot provide this report? Can I increase the costs in advance because of this and then have the work left undone? Who bears the additional costs? Has anyone ever had a similar case?