Hello everyone,
I have an offer from an architect (in-house architect of a construction company).
The plot is available (slope location) - planned single-family house with approx. 170m² living space.
The cost overview seems a bit low to me. What is not considered here? Could there be additional costs? Please help me:
Shell construction works
Scaffolding work 4,000.00
Earthworks 13,500.00
Masonry including clinker 58,000.00
Reinforced concrete work 52,000.00
Total shell construction works 127,500.00
Interior finishing works
Carpentry and timber construction works 8,500.00
Roof covering 8,500.00
Roof windows with shutters 2,500.00
Plumbing work 7,500.00
Thermal insulation of roof and
Cladding of the roof interior 6,500.00
Garage roof waterproofing 1,800.00
Metalworker work 2,500.00
Plaster and stucco work 12,500.00
Tiling and wall panel work 3,000.00
Screed work 2,500.00
Floor covering work 11,000.00
Heating, gas, water, wastewater installation 22,000.00
Solar system 7,500.00
Electrical installations 11,000.00
Ready-made windows with shutters 17,000.00
Front door 2,500.00
Garage door (up-and-over door) 700.00
Ready-made door elements 2,500.00
Total interior finishing works 130,000.00
Shell + interior finishing 257,500.00
Outdoor facilities
Garden facilities 3,000.00
Terrace 1,800.00
Pathways 3,000.00
Total outdoor facilities 7,800.00
Incidental construction costs
Architect / engineer services 5,000.00
Surveying costs site plan 2,000.00
Fine staking out 800.00
Building location measurement 1,100.00
Total incidental construction costs 8,900.00
House connection costs
Gas 2,500.00
Water 2,500.00
Wastewater 4,200.00
Electricity 2,400.00
Telecom 600.00
Total house connection costs 12,200.00
Total construction costs 286,400.00
Plot costs
Plot 500m2 x €195.50 97,750.00
Acquisition costs, notary, etc. 8,400.00
TOTAL COSTS 392,550.00
I have an offer from an architect (in-house architect of a construction company).
The plot is available (slope location) - planned single-family house with approx. 170m² living space.
The cost overview seems a bit low to me. What is not considered here? Could there be additional costs? Please help me:
Shell construction works
Scaffolding work 4,000.00
Earthworks 13,500.00
Masonry including clinker 58,000.00
Reinforced concrete work 52,000.00
Total shell construction works 127,500.00
Interior finishing works
Carpentry and timber construction works 8,500.00
Roof covering 8,500.00
Roof windows with shutters 2,500.00
Plumbing work 7,500.00
Thermal insulation of roof and
Cladding of the roof interior 6,500.00
Garage roof waterproofing 1,800.00
Metalworker work 2,500.00
Plaster and stucco work 12,500.00
Tiling and wall panel work 3,000.00
Screed work 2,500.00
Floor covering work 11,000.00
Heating, gas, water, wastewater installation 22,000.00
Solar system 7,500.00
Electrical installations 11,000.00
Ready-made windows with shutters 17,000.00
Front door 2,500.00
Garage door (up-and-over door) 700.00
Ready-made door elements 2,500.00
Total interior finishing works 130,000.00
Shell + interior finishing 257,500.00
Outdoor facilities
Garden facilities 3,000.00
Terrace 1,800.00
Pathways 3,000.00
Total outdoor facilities 7,800.00
Incidental construction costs
Architect / engineer services 5,000.00
Surveying costs site plan 2,000.00
Fine staking out 800.00
Building location measurement 1,100.00
Total incidental construction costs 8,900.00
House connection costs
Gas 2,500.00
Water 2,500.00
Wastewater 4,200.00
Electricity 2,400.00
Telecom 600.00
Total house connection costs 12,200.00
Total construction costs 286,400.00
Plot costs
Plot 500m2 x €195.50 97,750.00
Acquisition costs, notary, etc. 8,400.00
TOTAL COSTS 392,550.00