Security deposit / refusal to perform

  • Erstellt am 2015-09-22 23:14:51

Principio

2015-09-22 23:14:51
  • #1
Hello! Our architect is now demanding a security deposit before the completion of the contracts for work. The reason: we did not make the interim payments on time recently. However, we immediately objected to this because individual invoice items were not explainable to us. There was definitely no delay!
The invoices were issued to us with a payment term of 7 days. Initially, it was 14. Which payment term is generally customary?
The demand for the security deposit is a prerequisite for further cooperation.
She is announcing a refusal to perform if we do not agree to this.
What happens if I do not agree, and the architect carries out her threat? What options do I have to claim damages?
Best regards
 

Bauexperte

2015-09-23 00:43:37
  • #2
Good evening,

which advance payments have you made for what and for what reason were they paid late?

What ZZ was agreed upon in the contract with the ? architect?

What should the damages be based on?

Rhenish greetings from on the road
Construction expert
 

Principio

2015-09-23 09:22:16
  • #3
Good morning! No ZZ was recorded in the contract. Within the contract, payments were regulated according to HOAI (1.15% upon submission of the preliminary draft, 2.35% upon receipt of the building permit, 3.10% upon completion of the working plans ...). There was inconsistency and lack of verifiability because I received an installment payment twice, but with different construction sums. And this, although we discussed the construction costs in detail in a personal conversation beforehand. The damages claim could be based on the fact that I have to hire a new architect. This architect must assume liability for the entire planning and also perform double work, which will also be charged.
 

Musketier

2015-09-23 10:38:37
  • #4
How much later did you settle the amount then?

As an accountant, I know both the private perspective and the company's perspective.
A duplicate invoice should be resolved quite quickly.
In case of discrepancies in items, you can withhold the corresponding items and transfer the rest. This always works better than a complete withholding. A company is not a currency exchange after all and initially advances payments. Eventually, they want their money too.

By the way, unless a due date is agreed upon, immediate maturity applies legally to my knowledge.
 

Bauexperte

2015-09-23 19:49:14
  • #5
Good evening,

unless there are written agreements regarding the payment terms, the statutory payment period applies, which is derived from § 286 of the Building Code. But any specified payment term on an invoice "overrides" the legal provisions; nevertheless, you are in default after 30 days - with all consequences.

A security deposit can only be demanded if it was contractually agreed upon beforehand. So you should check your contract.


You are proceeding in a piecemeal manner (cool term Volker). In this respect, I cannot say anything about the possibility of compensation. Legally, I am not allowed to consider it anyway ;)

Rhenish greetings
 

Bieber0815

2015-09-23 21:42:26
  • #6
What exactly does that mean? Are you supposed to provide a bank guarantee, deposit a cashier’s check, entrust your mother-in-law? Or maybe transfer cash? How much? Just curious ... If you have paid the invoices and have a contract with the architect, he cannot simply withdraw, INAL. On the other hand: if he refuses to perform, you won’t be happy either if you have to force him to render the services (through legal action). So there is either an amicable agreement on continuing the cooperation (talk to each other!) or you go your separate ways as quickly as possible. If the latter applies, you have to see how to get out of the affair as gracefully as possible.
 

Similar topics
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.12.2013Pre-planning with the architect - is having your own floor plan sensible?18
10.03.2017Payment of the architect16
18.08.2017First invoice for earthworks and base slab due25
16.02.2018Stress with the architect - naively signed the preliminary contract17
29.01.2019Responsibility of the architect in case of KfW interest and further matters148
19.08.2018Strategically well-planned handover completion under building supervision11
30.11.2018Architect's Fee - Experiences10
28.02.2019HOAI or why architects have no interest.....38
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
14.04.2020Security deposit according to §650 of the Building Code20
11.03.2020Architects invoice - Amount okay?13
13.07.2020Developer does not want to offset lump-sum damages with installments19
02.02.2021The contractor wants to issue an invoice for planning services60
30.03.2022Terminate the contract with the general contractor "early"22
18.01.2023Architect performance phase 1-4 - Which documents are required?33
25.12.2023Behavior in case of imminent delay by the property developer48
10.12.2024Approximate costs for building design by an architect15

Oben