Hello everyone,
we are building with a general contractor. According to the construction description, the following point is included:
"The preparation of all building application documents"
Now today, the architect of the GC writes to us that we must commission a drainage plan because she needs it to complete the building application. How would you see this, who is responsible and who has to pay for the drainage plan?
Thanks in advance.