Payment plan

  • Erstellt am 2015-09-22 19:42:10

Pamiko

2015-09-22 19:42:10
  • #1
Hello,

today we received from a company, with whom we are in advanced planning stages, the payment schedule included in their standard contract.
How do you evaluate this? Do the payments actually correspond to the respective construction progress.

The construction sum is about 200,000 EUR and it is being built without a basement.

2.0% upon submission of the building application/building notification
5.0% upon issuance of the building permit
15.0% upon concreting the foundation slab (main house)
15.0% upon laying the ceiling over the ground floor
11.0% upon concreting the ring beam (main house)
12.0% upon erection of the roof truss (main house)
15.5% upon installation of the windows (excluding the front door)
11.0% upon application of the interior plaster
6.0% upon laying the underfloor heating pipes
3.0% upon laying the screed
3.0% upon application of the exterior plaster
1.5% upon acceptance

I am grateful for any opinion.

Regards
 

nordanney

2015-09-22 20:11:54
  • #2
Paying too much too early. When the windows are installed, you have already paid 75%! If your construction company then says "Goodbye," you won’t be able to finish the house with the remaining amount. 98.5% must be paid, even if there is no heating, no sanitary installation, and no electrical installation yet?!
 

Bieber0815

2015-09-22 21:22:12
  • #3
I agree with my predecessor; furthermore, I would particularly criticize this point, as I cannot see any service here. You should definitely renegotiate and be sure to obtain a second offer.
 

ypg

2015-09-22 21:38:11
  • #4




Planning, energy calculations, building application documents, logistics, tenders, statics, execution plans... this should be covered by the first two items, however, I do not know the costs of these items.
 

Pamiko

2015-09-23 09:06:36
  • #5
That was actually my thought as well. After the first two points, all the architectural services, etc. have already been provided. In our case, we would be at around 14,000 EUR. I actually thought that these two points were okay.

Otherwise, the previous comments also correspond to my assessment. There is obviously an urgent need for discussion with the company.

Based on the above-mentioned points: Could someone give an assessment of what percentage should be paid at most at which stage (so that it would still be acceptable)? How much, for example, after the first floor? How much after the second floor? How much after the roof and windows?...
 

Pamiko

2015-09-23 14:29:28
  • #6
I have just received the hint from the construction company upon inquiry that sanitary and electrical installation is done before the interior plaster and that a separate deduction can be made for that to make it clear. How would that then look? Accordingly, about 86% would be paid by the time electrical, sanitary, and interior plaster are completed.

That is too much, right? ([Boden- und Wandbeläge sind nicht Bestandteil des Vertrages])
 

Similar topics
27.02.2015Burglary-proof windows?33
03.06.2014Interior design - windows14
16.01.2018Is an extra charge for colored windows realistic?19
18.06.2014Inspector defect identification, determination of window installation10
18.05.2016Help needed with window arrangement!32
21.07.2014Installation of controlled residential ventilation - in the ceiling or outside?20
27.05.2015Huge problem with condensation on the window34
20.12.2019Trefz window prices and experiences?14
26.01.2015Window between two rooms13
13.03.2015Opinions on window parapet height sought30
09.04.2015For porthole, special regulations? Window, single-family house 1.5 stories.18
18.05.2020Proper Ventilation/Drying of Interior Plaster / Drying Time21
09.01.2017Newly built city villa with a granny flat and double garage72
09.12.2017Surcharge for installing large-format tiles88
09.08.2017Is exterior plastering possible before interior plastering in summer?10
01.09.2018Offer for heating / sanitary / ventilation - is it realistic?55
19.10.2020Cat. 7 network from main house to annex underground27
22.04.2021Costs for the heating & sanitary trade86
09.06.2021Housekeeping room room without window - is the ventilation system sufficient?26
12.09.2023Tile installation with additional costs for large format11

Oben