Hello,
today we received from a company, with whom we are in advanced planning stages, the payment schedule included in their standard contract.
How do you evaluate this? Do the payments actually correspond to the respective construction progress.
The construction sum is about 200,000 EUR and it is being built without a basement.
2.0% upon submission of the building application/building notification
5.0% upon issuance of the building permit
15.0% upon concreting the foundation slab (main house)
15.0% upon laying the ceiling over the ground floor
11.0% upon concreting the ring beam (main house)
12.0% upon erection of the roof truss (main house)
15.5% upon installation of the windows (excluding the front door)
11.0% upon application of the interior plaster
6.0% upon laying the underfloor heating pipes
3.0% upon laying the screed
3.0% upon application of the exterior plaster
1.5% upon acceptance
I am grateful for any opinion.
Regards
today we received from a company, with whom we are in advanced planning stages, the payment schedule included in their standard contract.
How do you evaluate this? Do the payments actually correspond to the respective construction progress.
The construction sum is about 200,000 EUR and it is being built without a basement.
2.0% upon submission of the building application/building notification
5.0% upon issuance of the building permit
15.0% upon concreting the foundation slab (main house)
15.0% upon laying the ceiling over the ground floor
11.0% upon concreting the ring beam (main house)
12.0% upon erection of the roof truss (main house)
15.5% upon installation of the windows (excluding the front door)
11.0% upon application of the interior plaster
6.0% upon laying the underfloor heating pipes
3.0% upon laying the screed
3.0% upon application of the exterior plaster
1.5% upon acceptance
I am grateful for any opinion.
Regards