Hello everyone,
I have received the following cost breakdown and payment schedule from our general contractor.
We are building 220m² living space on two levels (without a basement), with the ground floor being larger and therefore the flat roof.
Except for the floor coverings, everything is basically included.
Is this okay so far? It is difficult to make the items exact, if you really go into it, you have certainly paid too much. For example, even without a ventilation system, blinds, stairs, and a glued tile, 99% would have to be paid.
Net Gross
Planning and Energy Saving Ordinance Calculation €1,900.00 €2,261.00
Shell construction including earthworks and drainage €85,874.00 €102,190.06
Stair system with railing €8,788.00 €10,457.72
Interior plaster €12,410.00 €14,767.90
Exterior plaster as ETICS €28,989.00 €34,496.91
Carpentry/Roofing/Insulation €20,300.00 €24,157.00
Sheet metal work/flat roof €14,654.00 €17,438.26
Windows with window sills and blinds €29,584.00 €35,204.96
Interior doors/front door €14,348.00 €17,074.12
Screed €8,787.00 €10,456.53
Tiling work €20,521.00 €24,419.99
Floor coverings - € - €
Painting work €9,042.00 €10,759.98
Sanitary/Heating/Ventilation €52,710.00 €62,724.90
Electrical €10,278.00 €12,230.82
Completion of foundation slab €25,000.00 7%
Completion of ground floor ceiling €45,000.00 12%
Completion of upper floor ceiling €40,000.00 11%
Completion of main roof €25,000.00 7%
After window installation €25,000.00 7%
Completion of flat roof €25,000.00 7%
Completion of interior plaster €30,000.00 8%
Completion of screed €20,000.00 5%
Completion of full thermal insulation €30,000.00 8%
Start of tiling work €30,000.00 8%
Completion of heating €30,000.00 8%
After sanitary final assembly €30,000.00 8%
After completion of interior area €20,000.00 5%
Final invoice after acceptance €3,640.00 1%
Total €378,640.00 100%
There is also a 5% security deposit by guarantee.
edit: ah, why is there no table feature here..

I have received the following cost breakdown and payment schedule from our general contractor.
We are building 220m² living space on two levels (without a basement), with the ground floor being larger and therefore the flat roof.
Except for the floor coverings, everything is basically included.
Is this okay so far? It is difficult to make the items exact, if you really go into it, you have certainly paid too much. For example, even without a ventilation system, blinds, stairs, and a glued tile, 99% would have to be paid.
Net Gross
Planning and Energy Saving Ordinance Calculation €1,900.00 €2,261.00
Shell construction including earthworks and drainage €85,874.00 €102,190.06
Stair system with railing €8,788.00 €10,457.72
Interior plaster €12,410.00 €14,767.90
Exterior plaster as ETICS €28,989.00 €34,496.91
Carpentry/Roofing/Insulation €20,300.00 €24,157.00
Sheet metal work/flat roof €14,654.00 €17,438.26
Windows with window sills and blinds €29,584.00 €35,204.96
Interior doors/front door €14,348.00 €17,074.12
Screed €8,787.00 €10,456.53
Tiling work €20,521.00 €24,419.99
Floor coverings - € - €
Painting work €9,042.00 €10,759.98
Sanitary/Heating/Ventilation €52,710.00 €62,724.90
Electrical €10,278.00 €12,230.82
Completion of foundation slab €25,000.00 7%
Completion of ground floor ceiling €45,000.00 12%
Completion of upper floor ceiling €40,000.00 11%
Completion of main roof €25,000.00 7%
After window installation €25,000.00 7%
Completion of flat roof €25,000.00 7%
Completion of interior plaster €30,000.00 8%
Completion of screed €20,000.00 5%
Completion of full thermal insulation €30,000.00 8%
Start of tiling work €30,000.00 8%
Completion of heating €30,000.00 8%
After sanitary final assembly €30,000.00 8%
After completion of interior area €20,000.00 5%
Final invoice after acceptance €3,640.00 1%
Total €378,640.00 100%
There is also a 5% security deposit by guarantee.