JOERG24
2009-03-10 13:38:46
- #1
Hello originally I had planned to install perimeter insulation made of XPS below the base on a bitumen thick coating. I also wanted to insulate the base with XPS (ribbed plaster carrier board) A studded membrane was then supposed to be applied to the "smooth" surface for water drainage Now I saw today that the foundations are executed in earth shuttering construction. So the thickness varies greatly. Below the base there is now a very uneven surface that I probably cannot cover with Styrodur. How can I now achieve the planned sealing and insulation there? Or is a corresponding treatment below the base not necessary?