Meaningful sequence of tasks

  • Erstellt am 2015-08-16 17:47:04

Pardun

2015-08-16 17:47:04
  • #1
Hello,

my shell construction has been standing for several years now, and I have also been living in it for 2 years. I am financially fluid again and want to continue.

What would you recommend and why:

- Equip balconies with flooring and railing or ...
- Have the house plastered

What is usually done first?

Thanks for the help!
 

ypg

2015-08-16 22:40:37
  • #2
Shell construction? I would first install windows! :D

Hello first of all,
surely you don't mean a shell construction if you already live inside.
I would start with the work that protects the house or components and where the substance/product/component is endangered due to weather influences.

Plastering would probably be in order :)
 

Bauexperte

2015-08-16 22:48:46
  • #3

What exactly does that mean?
Rhenish greetings
 

Pardun

2015-08-17 18:15:48
  • #4
Hehe, shell construction is really the wrong term. It was built in 2001. My father and I did a lot ourselves, which is why moving in took a very long time.
 

HilfeHilfe

2015-08-18 07:44:53
  • #5
Well, you have to know what is especially important to you. [Vollwühloase] inside or cleaning for neighbors outside :)
 

ypg

2015-08-23 00:51:16
  • #6
So? What is important to you?

P.s. I find the year 2001 quite bizarre when you think about the initial question :cool:
 

Similar topics
14.11.2011Shell construction still this year15
05.09.2015Cracks in masonry (shell construction)14
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
24.04.2015Buy tiles during shell construction24
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
27.02.2015Purchase shell construction and complete it including financing15
11.02.2016Cost per cubic meter of built-up shell space14
07.05.2016Buying a shell construction - Experiences21
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
20.04.2017Payment plan with 35% after the shell construction, okay?10
05.05.2017Rough construction flat-rate offer - forgotten necessary items11
06.09.2017Add a wind catch later to the shell construction17
07.10.2017From when must the shell construction be dry or sealed?16
18.12.2017Offers for single-family house shell construction and basement received - your assessment?21
31.01.2022Possible savings in self-performed structural work37
27.08.2018New building shell construction selection: Choose a company or architects?52
18.09.2018No offer for electrical work - must the shell construction be stopped?12
09.10.2018Costs for shell construction and roof covering/insulation - fixed price offer okay?25
09.01.2019Final invoice for shell construction (200 sqm, clinker, without basement, roof) ok?24
26.06.2019Shell construction offer - what do you think?10

Oben