Lobster
2018-04-12 10:24:17
- #1
Hello everyone,
we applied for construction power in March assuming that the connection would be available 2-4 weeks later.
Now we have received feedback that many projects have accumulated over the winter and therefore the construction power will only be available in 8-9 weeks. We absolutely cannot wait that long, that would throw the entire schedule off.
If we cannot bring the date forward, we need alternatives!
We are developing a gap site – so we have no "neighbor construction" from which we could draw power.
One possibility would be a large emergency generator, which would also make considerable noise. I don’t want to upset the workers right from the start.
Even if that might not be an ideal start with the new neighbors, maybe someone with a "normal" power connection could help out from the garden or similar?
Did anyone happen to have a similar problem? I found some who forgot to apply for construction power in time but none who reported a solution.
Thanks in advance
we applied for construction power in March assuming that the connection would be available 2-4 weeks later.
Now we have received feedback that many projects have accumulated over the winter and therefore the construction power will only be available in 8-9 weeks. We absolutely cannot wait that long, that would throw the entire schedule off.
If we cannot bring the date forward, we need alternatives!
We are developing a gap site – so we have no "neighbor construction" from which we could draw power.
One possibility would be a large emergency generator, which would also make considerable noise. I don’t want to upset the workers right from the start.
Even if that might not be an ideal start with the new neighbors, maybe someone with a "normal" power connection could help out from the garden or similar?
Did anyone happen to have a similar problem? I found some who forgot to apply for construction power in time but none who reported a solution.
Thanks in advance