Leak test in new construction

  • Erstellt am 2015-11-29 07:25:05

ostsee

2015-11-29 07:25:05
  • #1
Hello everyone,

we have just completed a construction contract and I am now organizing all the documents.

I noticed that the leak test according to DIN EN 1610 (air) was carried out at the start of construction and only 2 meters of pipe were tested. Apparently, these were the 2 meters of piping laid under the floor slab. That was in March 2015.

In August or September, the sewage and rainwater pipes were then completed and connected to the shaft.

Is the initial test sufficient or should the completed system be tested?

I have not yet received a response from the developer regarding this.

Thank you very much!

Baltic Sea
 

Sebastian79

2015-12-01 07:52:15
  • #2
Finished system must be checked from the connection point (=channel transfer shaft).

Coming up for me on Friday... Another 350 euros gone :(
 