Good morning,
our financier is currently asking for the KFW online confirmation.
The site manager told us that the survey must take place first, then the architect plans and subsequently, together with the building application, the KFW online confirmation is requested through the engineering office (approx. 10 working days).
The financier says this is nonsense - it can also be applied for beforehand based on details such as volume/area etc. and energy efficiency, e.g. KFW 40.
What is the actual procedure now?! :)
our financier is currently asking for the KFW online confirmation.
The site manager told us that the survey must take place first, then the architect plans and subsequently, together with the building application, the KFW online confirmation is requested through the engineering office (approx. 10 working days).
The financier says this is nonsense - it can also be applied for beforehand based on details such as volume/area etc. and energy efficiency, e.g. KFW 40.
What is the actual procedure now?! :)