Hello,

how do you handle your house keys during the construction phase?
So far, the key for the construction door was always kept in a fixed place.
Now that we have our front door, I actually don’t want to do that anymore, especially for protection against unauthorized copies...
However, it is also difficult to impossible for me to always bring the key to the construction site. And since different tradespeople are currently working in the house, I can’t just give the key to one of them...

I was already thinking about some kind of key safe to at least have a bit of protection.
Ideally, I would prefer a safe with some kind of data logger so that I know who was in the house and when (also to possibly trace any damage in the house).
Does anyone have experience with this? Is there maybe such a thing available for rent for 5-6 weeks?
 

Pumbaa

2018-12-27 06:34:20
  • #2
The cylinder from the construction lock remained with us and was only replaced at the house acceptance.
 

haydee

2018-12-27 06:41:51
  • #3
With us, the correct lock was only installed upon handover

Would install a cheap interim lock
 

Müllerin

2018-12-27 07:34:33
  • #4
Exactly, put in a cheap lock. We had 3 keys for it. One for us, one for the construction supervisor, and the 3rd stayed on site for quite a long time - until the staircase was installed (it came very late), then I didn’t want that anymore, also because of the insurance. This one was then alternately held by the plumber and the electrician, because they had the most work and were on site the longest.
 

ypg

2018-12-27 12:51:37
  • #5


Same with us. During the construction phase, every trade from the general contractor had a master key. Only at house handover did we get a "real" lock with three keys for us.
 

Nordlys

2018-12-27 12:56:09
  • #6
So here as well.
 

Similar topics
07.06.2017Only financing during the construction phase21
22.02.2020Construction phase - what should be better avoided during the construction phase29
14.06.2021Expert during the construction phase22
13.07.2021Which consultants and analyses are appropriate during the construction phase?15
20.06.2022Access to house and garage: key vs code keypad vs fingerprint24

Oben