Hausi20
2020-03-09 19:33:07
- #1
Hello everyone,
we are building a turnkey project and the condensing boiler was installed by the construction company or its subcontractor in the attic above the upper floor.
We have removed the attic insulation and will carry it out as a personal contribution. The construction company's structural requirement is that the attic should have 20 cm thick insulation (WLG 035) throughout the entire area. The construction company told us that their subcontractor will install the heating system and apply the corresponding insulation underneath it. We can then insulate the attic afterwards.
Now we have seen that there are only 10 or 11 cm of insulation (styrofoam) under the heating system. Is it sufficient if we apply 20 cm of insulation around the system, or is the system already incorrectly installed on the 10/11 cm insulation? Shouldn't there also be a wooden board or similar in that area?

we are building a turnkey project and the condensing boiler was installed by the construction company or its subcontractor in the attic above the upper floor.
We have removed the attic insulation and will carry it out as a personal contribution. The construction company's structural requirement is that the attic should have 20 cm thick insulation (WLG 035) throughout the entire area. The construction company told us that their subcontractor will install the heating system and apply the corresponding insulation underneath it. We can then insulate the attic afterwards.
Now we have seen that there are only 10 or 11 cm of insulation (styrofoam) under the heating system. Is it sufficient if we apply 20 cm of insulation around the system, or is the system already incorrectly installed on the 10/11 cm insulation? Shouldn't there also be a wooden board or similar in that area?