casaro
2022-03-30 09:38:17
- #1
Hello,
new here, so please forgive any mistakes. We have a work contract with a general contractor, which roughly states the following:
The GC sent us a preliminary draft of the work plans several months ago. However, there were still some errors in them and we had some change requests. Some were incorporated, some were not. This went back and forth several times, and as of today, we have not yet received a work plan that is completely free of errors. However, the house is already being built intensively. The shell is now almost finished and as far as we can tell, it was also built “correctly.” That means the way we want it and not as shown in the preliminary drafts of the work plan.
We have pointed out to the GC several times that we have not yet received an error-free work plan and therefore cannot formally approve anything. I somehow don’t understand why this is being ignored by the GC. I see this rather disadvantageous for the GC because he is somehow building at his own risk. But maybe I am wrong. The following questions:
new here, so please forgive any mistakes. We have a work contract with a general contractor, which roughly states the following:
The contractor prepares, at his own expense, both the work and detailed planning required for him as well as the necessary static calculation, and, if required, the structural safety and fire protection certificate.
Before construction begins, the work plans (scale 1:50) must be submitted to the client and signed off by him for construction approval.
The GC sent us a preliminary draft of the work plans several months ago. However, there were still some errors in them and we had some change requests. Some were incorporated, some were not. This went back and forth several times, and as of today, we have not yet received a work plan that is completely free of errors. However, the house is already being built intensively. The shell is now almost finished and as far as we can tell, it was also built “correctly.” That means the way we want it and not as shown in the preliminary drafts of the work plan.
We have pointed out to the GC several times that we have not yet received an error-free work plan and therefore cannot formally approve anything. I somehow don’t understand why this is being ignored by the GC. I see this rather disadvantageous for the GC because he is somehow building at his own risk. But maybe I am wrong. The following questions:
[*]Is there a "trap" we could fall into if building continues intensively even though the work plan has not been finally approved?
[*]Could we possibly refuse interim payments (due, for example, when a floor in the shell is completed) on the grounds that the work plans must be approved before construction begins? (perhaps more something for the lawyer who reads the entire work contract, but maybe someone has concrete experience).