Boltiker
2018-05-05 19:56:29
- #1
Hello everyone,
when creating the base slab, the subcontractor made a mistake. The slab and the foundation were made too short. As a result, we imposed a construction stoppage until the matter was clarified. In the meantime, the engineering firm made a proposal on how the problem could be resolved (extension of the base slab, etc.). The general contractor additionally extended the warranty for the problem areas. This is limited to demolition and settlement of the base slab.
We had the proposal from the structural engineer reviewed by an expert. He classified the measures as harmless. Subsequently, we issued a construction release.
Now we have received a letter from the general contractor. We are supposed to sign an agreement stating that the service is free of defects and contractually accepted (perhaps still acceptable to some extent).
Furthermore, no claims are to be asserted (in particular not for damages reduction, claims arising from delay, etc.) We do not find this acceptable. Our opinion is that we have the right to claim damages, which is regulated by law. So the general contractor cannot simply say that we will not continue construction if he does not agree.
Nothing has been done at the construction site for a month. We assume that the handover deadline will not be met because of this. If we were to sign the agreement, we could not claim damages (rental costs, etc.).
What do you think is the correct procedure in this case? Can the general contractor simply refuse to continue construction because we might claim damages?
Thank you.
when creating the base slab, the subcontractor made a mistake. The slab and the foundation were made too short. As a result, we imposed a construction stoppage until the matter was clarified. In the meantime, the engineering firm made a proposal on how the problem could be resolved (extension of the base slab, etc.). The general contractor additionally extended the warranty for the problem areas. This is limited to demolition and settlement of the base slab.
We had the proposal from the structural engineer reviewed by an expert. He classified the measures as harmless. Subsequently, we issued a construction release.
Now we have received a letter from the general contractor. We are supposed to sign an agreement stating that the service is free of defects and contractually accepted (perhaps still acceptable to some extent).
Furthermore, no claims are to be asserted (in particular not for damages reduction, claims arising from delay, etc.) We do not find this acceptable. Our opinion is that we have the right to claim damages, which is regulated by law. So the general contractor cannot simply say that we will not continue construction if he does not agree.
Nothing has been done at the construction site for a month. We assume that the handover deadline will not be met because of this. If we were to sign the agreement, we could not claim damages (rental costs, etc.).
What do you think is the correct procedure in this case? Can the general contractor simply refuse to continue construction because we might claim damages?
Thank you.