General Construction Manager in Baden Württemberg

  • Erstellt am 2022-02-19 17:46:36

LadyDisaster

2022-02-19 17:46:36
  • #1
Hello everyone,

we want to build a prefabricated house 117 sqm in Baden Württemberg.
Now our prefabricated house provider told us that we also need the signature of an overall construction manager for this.

The architect commissioned for planning and building application preparation (was commissioned by the prefabricated house provider) cannot help us with who we need/can contact for this.

Do you possibly have experience with how we can solve this problem? And if yes, what the approximate additional costs are.

Best regards Sabine
 

11ant

2022-02-19 19:25:32
  • #2
A prefabricated house supplier is basically just a general contractor as well, so their site manager should also be considered the general construction manager. The fact that the house manufacturer is asking for this is pretty bold – or did you skimp in the wrong place and choose someone who expects the foundation slab to be provided "on site"?
 

LadyDisaster

2022-02-19 20:04:28
  • #3


You are basically right there, if we were building in Bavaria, that would also be the case. Also with this provider, who has a "partnership" with a foundation slab builder that they sell it through. (to clarify, we live near the Bavaria/Baden-Württemberg border) In Baden-Württemberg, however, there must be some rule that generally an overall site manager is required.
 

11ant

2022-02-19 22:48:07
  • #4
Then the house manufacturer is probably more confused by the term (?) or what prevents him from naming his construction manager as such? - the municipality probably means a construction manager who is the contact person for the authority throughout the entire construction period, responsible for the timely submission from the construction notification to the completion notification.
 

LadyDisaster

2022-02-22 19:20:29
  • #5
Thanks for your reply. Unfortunately, besides what felt like 1000 phone calls and a sick child, I forgot to answer. Don't ask how many times I was sent from one person to another. Eventually, I ended up with the person responsible for building applications in the planned district. Apparently, in BaWü it really is the case that a construction manager has to be there who takes responsibility for everything and thus supervises everything. However, this does not seem to apply to prefabricated houses, because it is enough if the construction manager from the foundation builder and the one from the prefabricated house sign the building application. If it were a solid house, it wouldn’t be possible without this overall construction manager. So, all in all, lots of drama and frayed nerves for nothing. -.-
 

Sabine_2412

2022-02-24 19:38:45
  • #6
Hello LadyDisaster,

we are currently facing the same problem in Baden-Württemberg.

The prefabricated house company only signs the form for a hefty fee. You know what construction management costs on the "open market" (LPH 8).

I can still ask the basement company, but they won’t take responsibility for everything that comes after the basement trade either.

I’m quite at a loss and have already thought about construction-related controlling by TÜV or Dekra. But will that be enough?

Best regards

Sabine
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
26.10.2013Planning/Architect, possible execution by "prefabricated house providers"21
29.10.2013Property reserved, construction financing plan, architect/building permit application21
28.02.2015Building application submitted/open detailed questions/looking forward to suggestions39
15.06.2015Garage - Building Application - Confusion36
27.01.2017Price-performance comparison: Which is the best prefabricated house provider?16
27.04.2017Carport deviation from the building application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?44
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
27.06.2018Prefabricated house provider with electrical installation as own work14
08.08.2018Neighbor objects after approved building application69
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
22.08.2019Who are the "most affordable & good" prefabricated house providers?13
09.10.2019Looking for affordable & good prefab house providers. (lower budget)62
30.01.2021The building authority rejects the building application because the house is planned too far back86
13.03.2021Opinion on various prefabricated house providers desired68
23.05.2021General contractor / prefabricated house provider with an existing BG (HOAI Phase 4)27