Hello everyone,

we have a prefabricated house built with a timber frame construction.

Just now I noticed a gap in a wall, which I don't think was this big before. (Pictures are attached)

Could it be that the wall has "settled"? The screed was applied yesterday.

Do you think this gap is too big and concerning? If yes, how should it be closed? I guess not by foaming :) I have the impression the manufacturer will just plaster over it when plastering.

Many thanks

Steffen



 

cschiko

2018-12-14 12:51:04
  • #2
Is this an interior wall? And Image 3 basically shows the view into the gap? Then it seems as if the gap on the other side is sealed with an insulating strip or something like that. Unfortunately, the images are only partially revealing, as it is not clear what kind of wall it is.
 

Skyfire

2018-12-14 13:41:22
  • #3
These are exterior walls. In the picture, you can basically see the view from the outside onto the wooden frame of the wall on the inside (so yes, picture 3 is the view of the gap from the outside). That is where the living room wall meets the bay window wall of the kitchen.
 

Skyfire

2018-12-15 16:23:32
  • #4
Not a single person has an opinion on this?
 

Caspar2020

2018-12-15 19:02:06
  • #5
Yes; but the images are not very informative. Furthermore, it is unclear to what extent they are system-related within the system of your prefabricated house builder; you can't really look through them.

It's best if you ask your site manager.
 

seat88

2018-12-15 19:24:49
  • #6
I would also contact the site manager about that. He should take care of it...
 

Similar topics
01.04.2020Construction Manager Area Neukirchen-Vluyn (Duisburg/Kleve/Wesel)10
10.02.2014Commitments from the construction manager - Trust relationship13
09.03.2014Construction manager missing10
13.11.2017Construction scheduling - Who has to create it? General contractor, site manager?11
15.01.2018Can a construction manager resign due to poor performance?16
22.04.2018Construction is continuously delayed - call the site manager?36
31.05.2019The construction manager does not come, does not check, or he doesn't care about anything16
12.08.2019First appointment construction manager - Tips?11

Oben