Front door or construction site door or side entrance?

  • Erstellt am 2017-05-07 09:13:33

305er

2017-05-07 09:13:33
  • #1
Hi, in just under 2 weeks our house construction with the foundation slab begins.

We are building with a general contractor or main contractor? I don't remember anymore. It is a turnkey house in solid construction, with architectural services, and the trades are awarded by them. The trades come from all over Germany.

We had the front door including the sidelights deducted and bought it ourselves, or rather ordered it this week.

In an email from the house building company it says:
"Please note that the front door must then be delivered and installed by you when our windows are installed. The shell must be closed so that we can continue with the work. If you install a construction site door, additional finishing costs for the later installation of the 'real' front door on site will be incurred. These costs are to be paid separately on site by you according to effort."

One thing I don’t understand is that I have the service for the complete plastering of the house and the complete screed in the contract.
Why do I have to expect additional costs in this regard if the actual front door is only installed at the end and the workers have to plaster or lay the screed again afterwards?
Theoretically, it should only be the transportation that I have to pay for again, right? Because material and labor are included anyway.
But many also charge well for transportation, especially if they come from Hanover and we build in Lampertheim.

The site manager said on Tuesday that I would probably only have to pay about €100 for the construction site door. But of course, I don’t have this in writing.

If I understand correctly and install a construction site door, I pay for it and at the end the actual door with frame comes and then the screed etc. is reworked, right?

How can I avoid this?

A coworker of mine, who also sells front doors, said:
If it is not possible otherwise and to avoid costs and damage to the expensive front door, I should simply install it from the start, wrap it well and lock it!
The construction workers should then simply enter the house from the back via the terrace.

Is this possible? Can I insist that they then go sideways or through the back of the house in order to protect the door?

Attached is our construction schedule and the floor plan with the "entrances."

Thanks a lot in advance!

Best regards

 

Nordlys

2017-05-07 10:15:02
  • #2
I would arrange with the door supplier that they install the front door only as a frame without filling, as a chipboard will be inserted, and the filling will be delivered and installed later when everything is safe. That’s how we do it. See picture. Frame and handle are well protected by foils. Karsten
 

Curly

2017-05-07 11:16:47
  • #3
But that only works with front doors that have a visible panel, right? Back then we also got the front door ourselves. Our construction company then installed a construction site door, and only after the house was almost finished did we have the actual door installed. We didn’t pay anything extra. How are the craftsmen supposed to get through the patio door, is it lockable from the outside? Best regards Sabine
 

305er

2017-05-07 11:28:21
  • #4
Hi, that's right. No, it cannot be locked from the outside.
 

11ant

2017-05-07 14:15:41
  • #5


I think Nordlys actually meant the "sash" there. So that you only install the frame of the door (which can already be plastered) and protectively tape it off; the door sash - whether it has panels or not - is not yet hung, nor are its hinges screwed in, but instead a chipboard is inserted in which the construction site door can be mounted.

Yes, that is a practical solution. It wouldn’t be a problem for the craftsmen to "go around the back."

.



The construction site door covers parts of the reveal where the final door is fitted. You then have to work around that and complete the work at a later stage. If the contractor supplied the door, they could better coordinate the replacement timing and avoid the double effort involved. It is perfectly correct and objectively justified not to absorb the additional cost on behalf of the client.
 

305er

2017-05-07 16:40:32
  • #6
But the frame and the side panel are also not exactly cheap. And they will probably have to work on them more often as well.
 

Similar topics
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
08.05.2014Most moisture from screed?25
10.05.2015Screed uneven - defect removal refused52
10.08.2015In which season of the year is it best to bring screed into the basement10
13.04.2017Screed with gold sand17
28.04.2016Order screed - plaster14
27.05.2016Plastic fittings/water pipes and insulating underfloor heating beneath screed?40
07.08.2016Upper floor without screed - only concrete floor15
08.06.2016Questions about underfloor heating - new subfloor/screed/granite tiles14
31.07.2016Screed does not extend into the reveals at windows / terrace doors on the ground floor12
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
31.10.2016Heating the screed with the utility provider?!12
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
05.04.2017Super disaster - water pipe burst, screed damp31
09.04.2017Screed is too low. Are there standards for this?16
30.04.2017Screed applied too high - room height consequently lower11
05.08.2017Screed necessary? Unfinished but insulated attic23
16.01.2020Experiences with aluminum front doors from different manufacturers RC316

Oben