Floor-level installation of a ceramic shower tray

  • Erstellt am 2016-09-03 15:47:22

inma75

2016-09-03 15:47:22
  • #1
Hello everyone.

Installation of a ceramic shower tray, 120x90cm, approx. 40kg heavy. In the end, the shower tray should be flush with the floor. On the right and front sides, there are walls respectively; on the left, there is an anhydrite screed including Styrofoam insulation (because of underfloor heating, which of course runs only outside the shower area), the height of this screed is about 6cm, after tiling approx. 7.2cm. The area at the back is about 40cm (160cm between both walls minus 120cm width of the tray) and must be "filled" with cement screed (since it is a wet area). This area is not problematic, as the cement screed will be just as high as the anhydrite screed (thus 6cm). More problematic is the area under the shower tray, which has a self-height of 3.5cm. For the substructure, there remain approx. 3.5cm. A cement screed with a thickness of 3.5cm alone would of course be problematic.

Two questions: 1.) Support the shower tray with 4 rows of aerated concrete blocks underneath (each 90cm, 10cm, 3.5cm) and fill the resulting gaps with cement screed; appropriate waiting time until everything has "settled"; in my opinion, due to the blocks, a stable substructure for the later embedding of the tray. (I do not think much of shower feet or Styrofoam or anything as a substructure). What do you think about that?

2.) When the substructure is dry, the tray is placed on top. What gives the tray its support? Its own weight, the silicone on the side walls. My question: Does this ceramic tray need to be additionally filled in the cavities underneath (see pictures) with leveling compound (Speis) or screed, or is this not necessary? In other forums, regarding this problem, it is said that for maintenance reasons, the tray must not be glued to the substrate with tile adhesive (which I do not intend to do either). Some line the underside of the tray with foil and then fill with leveling compound (fills the cavity effect, but no bonding).

I think the cavity under the tray is so shallow that it can remain as it is (i.e., unfilled) and I thus only fix the tray at the edge area with silicone on the floor. Silicone from below, silicone from the sides, own weight, the screed from the back (with separation tape between tray and screed), all this should provide sufficient fixation for the tray. What do you think about that?

PS: Sealing is clarified.
Regards!
 

inma75

2016-09-03 16:05:57
  • #2
More photos
 

inma75

2016-09-03 16:06:59
  • #3
Overall image

 

Legurit

2016-09-03 16:09:13
  • #4
Normally there are carriers for that, right? With us, it lies on such a styrofoam carrier.
 

inma75

2016-09-03 18:11:16
  • #5
- I did not find a bracket for the (Villeroy & Boch) cup at Villeroy & Boch, which suggests that installation with a bracket is not intended. Your answer prompted me to measure. The deepest spots under the cup in the rim area range from 1.5 to 2 cm. Therefore, I am increasingly convinced that the cup is only placed and fixed by applying moderate amounts of silicone. - But I am happy to be proven wrong. Regards
 

Mycraft

2016-09-03 18:19:50
  • #6
Well, there seem to be enough ribs below that serve as support. Therefore, a beam is probably not necessary.... but everything about it should be found in the technical documentation at Villeroy & Boch.
 

Similar topics
23.12.2015Villeroy & Boch O-Novo including WC seat experiences13
22.06.2016Substructure for terrace15
06.11.2017Villeroy & Boch Combipool Invisible26
18.02.2020Gutter sealed with silicone and rivets11
07.06.2022Which wall toilet: Villeroy & Boch, Geberit, Duravit???39
08.03.2021Screed qualities in the field of anhydrite / cement screed11
16.01.2022Joints of the wooden staircase with silicone18
18.07.2022On which surface should the shower tray be placed?11
04.07.2023New cement screed wobbles on new underfloor heating and insulation15

Oben