I know that usually the order is chosen the other way around. However, I would like to have the screed done first and then plaster. The reason is that I would like to have flush skirting boards and in my opinion, it is easier to achieve if the screed is already in the house.
Is there any reason not to swap the order?
Thanks and regards
Micha
I know that usually the order is chosen the other way around. However, I would like to have the screed done first and then plaster. The reason is that I would like to have flush skirting boards and in my opinion, it is easier to achieve if the screed is already in the house.