Drying time anhydrite screed

  • Erstellt am 2015-04-18 23:18:18

milkie

2015-04-18 23:18:18
  • #1
Hello everyone,

we have already done a bit of research on the internet, but have not yet found any really helpful information.
At the end of April/beginning of May, the screed will be laid with us ([Anhydrite screed thickness 65mm]). What drying time should be expected? When can spackling/wallpapering/painting begin, and when can the flooring be installed?
Thanks in advance.
Best regards, milkie
 

AlexR20

2015-04-19 19:07:39
  • #2
You should definitely plan for 4 weeks. It should dry out for 2 weeks, and then 2 weeks of curing heating are required. Walls can be done at any time. Provided you want to work in a sauna when it is heated up.
 

Bauexperte

2015-04-20 10:55:02
  • #3

You should ask your screed installer; it is hardly possible to answer that in general, as it depends on the additives and the outside temperature.


The screed is usually "walkable" after 3-5 days. The more interesting question is: do you want to work in mist and fog (heating to achieve readiness for covering) and risk wallpaper falling off or increased cracking?

I fully understand that builders are eager toward the end of the construction period. BUT drying times are necessary and should be adhered to. Hopefully you will enjoy your new home for a long time; a difference of 4-6 weeks should not matter ... or don’t you think so?

Best regards from the Rhineland
 

milkie

2015-04-20 11:58:56
  • #4
No, of course not. But it would be important to know approximately when we will continue for vacation planning, material procurement, etc. We don’t want to continue too early, but a rough estimate would be good. Then we will ask the screed layer tomorrow when he installs the insulation.
 

Kikolool

2015-04-22 13:21:24
  • #5
For us, it was 5 weeks. The moisture can also be measured regularly (there should be small flags on the floor). We said better to start one week later than one week too early. The tiler also had a say, because he also gives a guarantee on the flooring and can only provide it if the basic requirements (i.e., installation readiness) are met.

Alex
 

Similar topics
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
08.05.2014Most moisture from screed?25
10.05.2015Screed uneven - defect removal refused52
10.08.2015In which season of the year is it best to bring screed into the basement10
13.04.2017Screed with gold sand17
28.04.2016Order screed - plaster14
27.05.2016Plastic fittings/water pipes and insulating underfloor heating beneath screed?40
07.08.2016Upper floor without screed - only concrete floor15
08.06.2016Questions about underfloor heating - new subfloor/screed/granite tiles14
31.07.2016Screed does not extend into the reveals at windows / terrace doors on the ground floor12
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
31.10.2016Heating the screed with the utility provider?!12
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
05.04.2017Super disaster - water pipe burst, screed damp31
09.04.2017Screed is too low. Are there standards for this?16
30.04.2017Screed applied too high - room height consequently lower11
05.08.2017Screed necessary? Unfinished but insulated attic23
19.08.2017Technical room before installing screed: should the technology be painted now or later?16

Oben