morlad
2013-08-20 11:07:42
- #1
Hello,
my construction company has fallen behind schedule and wants to make up time with the screed. In my house, floating cement screed is to be used. Before the start of construction, I was told that the screed must dry for at least 28 days. Now that they are behind schedule, the site manager tells me that they will add a additive to the screed, which reduces the time to 14 days.
My question now is whether this is correct and if the quality remains the same?
Thanks in advance
Gerald
my construction company has fallen behind schedule and wants to make up time with the screed. In my house, floating cement screed is to be used. Before the start of construction, I was told that the screed must dry for at least 28 days. Now that they are behind schedule, the site manager tells me that they will add a additive to the screed, which reduces the time to 14 days.
My question now is whether this is correct and if the quality remains the same?
Thanks in advance