Bauen15/16
2016-03-23 12:59:29
- #1
I hope you can help me. We had our central ventilation system installed on the concrete floor for structural reasons. Now the screed should be poured. As we learned from the screed layer last week, he has to apply the screed in layers, one centimeter each day. This is due to the many pipes of the ventilation system. It is a flowing screed. Then the underfloor heating is installed on top, followed by screed again. When I was at the construction site yesterday, I saw that 7 centimeters of screed were poured at once. When I asked the employees, they said they always do it this way. They had never heard of [Zentimeteraufbau]! When I tried to reach the boss, he said he was not there when the [Zentimeteraufbau] was mentioned. When I explained my concern, the employee said everything was fine. There is no other procedure. I must have misunderstood something. How can one misunderstand something like that? Unfortunately, our site manager is no help either. He gives the same answer, everything is correct. Now we are afraid that the screed was poured all at once due to time pressure. How was it done for you?