Deficient architectural performance, delayed start of construction

  • Erstellt am 2017-09-07 00:47:18

Zaba12

2017-09-07 09:49:36
  • #1
Something like that must also be included with you.... If yes, then it becomes impossible and you can only hope for goodwill.
 

Matthias9541

2017-09-07 10:02:39
  • #2


Thank you for your feedback. The contract with the solid house provider was signed around June 2016. It took half a year for the first building application to be approved. The house would then have been located 1 m below the street level. The architect's statement was that there was no alternative to this. At first, I trusted him. Unfortunately, only after the approval of the first building application did I look into the whole thing more closely and then discovered an alternative that was compatible with the building regulations. The solid house provider has not commented on this deficiency to this day, very likely to avoid additional planning effort. Then it took another approx. 8 months until the second building application, including renewed static calculations, was approved; according to the solid house provider, the summer holidays extended the whole process. According to the plan, the house is now only 25 cm below the street level. As already mentioned, after the second building application was approved, the construction start meeting with the general contractor was supposed to take place. Originally, it was agreed in writing that the construction should start 30 days after the construction start meeting. Now the general contractor believes this agreement cannot be kept, as 4 out of 10 construction workers are seriously ill for a longer period, so construction can begin at the earliest at the end of the year or the beginning of the new year.
 

Matthias9541

2017-09-07 10:27:06
  • #3
Zaba12, thank you for your feedback. Under "Bauzeitgarantie" it says: "Der Auftragnehmer beginnt mit den Baumaßnahmen 30 Werktage nach der Vorlage der auflagefreien Baugenehmigung". The building permit has been available since July 26.
 

Joedreck

2017-09-07 10:31:25
  • #4
Does it also say anything about force majeure, etc.? Do not read only sentence by sentence and pick out details.
 

Bau-Schmidt

2017-09-07 10:48:37
  • #5
I only secured my financing 3 months after signing the contract. I already had an approval. For you, it will be a learning experience.
 

Matthias9541

2017-09-07 10:58:57
  • #6
Bau-Schmidt, smart decision, you were better than me there.
 

Similar topics
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
15.06.2015Garage - Building Application - Confusion36
28.11.2024Neighbor's lawsuit against approved building permit46
16.01.2017No building permit as long as the land is not developed?10
04.08.2017Building application or building notification15
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
25.11.2019Exemption procedure or building permit40
15.08.2021Duration until the issuance of the building permit in BW57
09.05.2021Price adjustment clause in the contract with the general contractor18
30.07.2021Is building without a building permit possible?26
09.07.2022Building with a general contractor - claim for additional costs shortly before the start of construction35
30.11.2021Fee notice for building application57
30.03.2022Terminate the contract with the general contractor "early"22
22.05.2022Tips for Waiting for Building Permit26
28.06.2024Building permit - is a lawyer useful?12

Oben