Matthias9541
2017-09-07 00:47:18
- #1
I want to build a single-family house with a solid house provider. This provider is responsible for the architectural services and subsequently delegates the construction project to a general contractor. I already owned the building plot before signing the contract. The building site is slightly sloping.
We had a strong interest in keeping the slope between the street and the house as small as possible. The responsible architect suggested placing the house about 1 meter lower than the street; the building regulations would have basically allowed a slope of about 25 cm, but the architect did not inform me of this, and I had to find this out myself after the approval of the first building application. The architect suggested 1 meter because the house entrance was located on the side, and a 3-meter distance to the neighboring plot had to be maintained. With a slope of 1 meter, two steps would have been necessary, which would have extended about 50 cm into the 3-meter distance to the neighboring house; 2.50 meters would have remained to drive past the stairs with a car to the garage. With a slope of 25 cm, five steps would have been necessary, and it would not have been possible to drive past the stairs with a car. Before the first building application, I asked the architect if there was an alternative to lowering the house by 1 meter; he denied it. The first building application was approved.
After the approval of the first building application, I found out that there had been an alternative: the house entrance would have only had to be moved to the other side. We then insisted on this; a second building application was submitted, which was approved after about half a year. According to the plan, there should now only be a slope of 25 cm between the street and the house.
This procedure has led to us having to pay interest on the loan commitment for 3 months now; so far, we have had to pay rent for about 8 months longer, with total costs of approximately 13,000 euros so far. This is now my first question: Who has to bear the costs, me as the client or the solid house provider?
After the second building application was approved, the construction startup meeting with the general contractor was supposed to take place. Originally, it was agreed in writing that construction should begin 30 days after the startup meeting. Now the general contractor believes that this agreement cannot be kept because 4 out of 10 construction workers are on long-term sick leave; construction can start at the earliest at the end of the year or the beginning of the new year.
It should also be noted that the solid house provider offered me an alternative general contractor who would start building immediately but, unlike my current general contractor, has hardly any references. The TÜV would inspect the construction project at all relevant phases; the costs would be borne by the current solid house provider.
Additional interest on the loan commitment and further rent will be incurred. This is now my second question: Who has to bear the costs, me as the client, the general contractor, or the solid house provider? Should I consult a specialist lawyer for construction law? How should I decide?
We had a strong interest in keeping the slope between the street and the house as small as possible. The responsible architect suggested placing the house about 1 meter lower than the street; the building regulations would have basically allowed a slope of about 25 cm, but the architect did not inform me of this, and I had to find this out myself after the approval of the first building application. The architect suggested 1 meter because the house entrance was located on the side, and a 3-meter distance to the neighboring plot had to be maintained. With a slope of 1 meter, two steps would have been necessary, which would have extended about 50 cm into the 3-meter distance to the neighboring house; 2.50 meters would have remained to drive past the stairs with a car to the garage. With a slope of 25 cm, five steps would have been necessary, and it would not have been possible to drive past the stairs with a car. Before the first building application, I asked the architect if there was an alternative to lowering the house by 1 meter; he denied it. The first building application was approved.
After the approval of the first building application, I found out that there had been an alternative: the house entrance would have only had to be moved to the other side. We then insisted on this; a second building application was submitted, which was approved after about half a year. According to the plan, there should now only be a slope of 25 cm between the street and the house.
This procedure has led to us having to pay interest on the loan commitment for 3 months now; so far, we have had to pay rent for about 8 months longer, with total costs of approximately 13,000 euros so far. This is now my first question: Who has to bear the costs, me as the client or the solid house provider?
After the second building application was approved, the construction startup meeting with the general contractor was supposed to take place. Originally, it was agreed in writing that construction should begin 30 days after the startup meeting. Now the general contractor believes that this agreement cannot be kept because 4 out of 10 construction workers are on long-term sick leave; construction can start at the earliest at the end of the year or the beginning of the new year.
It should also be noted that the solid house provider offered me an alternative general contractor who would start building immediately but, unlike my current general contractor, has hardly any references. The TÜV would inspect the construction project at all relevant phases; the costs would be borne by the current solid house provider.
Additional interest on the loan commitment and further rent will be incurred. This is now my second question: Who has to bear the costs, me as the client, the general contractor, or the solid house provider? Should I consult a specialist lawyer for construction law? How should I decide?