Cutout for wastewater pipe

  • Erstellt am 2016-05-20 16:16:00

MatzeGalle

2016-05-20 16:16:00
  • #1
Hello, first of all about me. I am a complete DIY novice and am currently building a single-family house. I have a quick question. I am standing in the shell construction on the first floor where the bathroom will soon be. The concrete ceiling has already been poured. My question: I cannot see any recess for a waste water pipe going down. Is it channeled into the wall or was the recess forgotten? Thanks
 

Mycraft

2016-05-20 16:25:17
  • #2
You surely have an execution plan that you have signed. Everything should be visible there. If nothing is available yet, it could also be that a core drilling will be done later. It’s putting the cart before the horse, but it happens.
 

MatzeGalle

2016-05-20 16:33:32
  • #3
I am having the plumbing installations done by another company and not by the construction company. However, I cannot reach anyone at the plumbing company.... probably already the weekend...
 

Mycraft

2016-05-20 16:50:50
  • #4
There is also an execution plan, after all, they don't just start building randomly. But in this case, communication was probably poor or non-existent, so each trade is doing its own thing... in other words, it comes down to a core drilling.
 

Similar topics
29.12.2015build without execution planning if...25
05.01.2016Execution planning first agreed upon - then excluded?43
21.07.2016Execution planning, scope22
27.07.2017Core drilling in the house - does it create a lot of dust inside?23
22.10.2020Building without execution planning - experiences whether this is possible?16