Hello,
we received an offer today for our drainage work from our civil engineer. Since I have no way to assess the offer at all, I would appreciate feedback.
Sewage and rainwater are to be connected to separate inspection shafts, and a leak test is to be carried out on both.
The offer lists the following costs each plus VAT:
Site setup 250
Laying pipe incl. 100KG, running meter 33.90
Leak test according to DIN with protocol and plan 670
A total of €3400 for approx. 50m.
Is the price okay? The leak test seems quite expensive to me.
Thank you
we received an offer today for our drainage work from our civil engineer. Since I have no way to assess the offer at all, I would appreciate feedback.
Sewage and rainwater are to be connected to separate inspection shafts, and a leak test is to be carried out on both.
The offer lists the following costs each plus VAT:
Site setup 250
Laying pipe incl. 100KG, running meter 33.90
Leak test according to DIN with protocol and plan 670
A total of €3400 for approx. 50m.
Is the price okay? The leak test seems quite expensive to me.
Thank you