Nina132
2015-06-23 15:48:12
- #1
Hello prospective homeowners,
as expected, our house construction is progressing much slower than advertised. I would like to hear some experiences in order to realistically look into the future. We are building a solid turnkey house with a construction company, which is led primarily by an architect’s office. We signed the contract in mid-March 2015, with a construction time of 9 months from groundbreaking. Some things (soil survey, heating, structural engineering, civil engineering) are handled externally (commissioned by us) or semi-externally (i.e., commissioned by the architect’s office).
Land, notary, construction financing, surveying – all taken care of directly.
The building application is approved, geothermal probe/pump applied for and approved.
The (external) soil survey has taken from the end of April until now (!!!!), and the surveyor has exceeded his promised timeline by 5 weeks.
Now we are waiting (again) for the structural engineer, only after that can the civil engineer be commissioned... The structural engineer apparently has a long queue, and thanks to the soil survey we are now at the very end again.
In March, before signing, it was said the house should be finished by the turn of the year.
I have calculated an additional two months on that, so until now I assumed moving in by the end of February/March 2016.
The crucial point is that I then have to move and apply for a new job.
What do you think is a realistic goal?
as expected, our house construction is progressing much slower than advertised. I would like to hear some experiences in order to realistically look into the future. We are building a solid turnkey house with a construction company, which is led primarily by an architect’s office. We signed the contract in mid-March 2015, with a construction time of 9 months from groundbreaking. Some things (soil survey, heating, structural engineering, civil engineering) are handled externally (commissioned by us) or semi-externally (i.e., commissioned by the architect’s office).
Land, notary, construction financing, surveying – all taken care of directly.
The building application is approved, geothermal probe/pump applied for and approved.
The (external) soil survey has taken from the end of April until now (!!!!), and the surveyor has exceeded his promised timeline by 5 weeks.
Now we are waiting (again) for the structural engineer, only after that can the civil engineer be commissioned... The structural engineer apparently has a long queue, and thanks to the soil survey we are now at the very end again.
In March, before signing, it was said the house should be finished by the turn of the year.
I have calculated an additional two months on that, so until now I assumed moving in by the end of February/March 2016.
The crucial point is that I then have to move and apply for a new job.
What do you think is a realistic goal?