Concealed installation / pipe laying in screed

  • Erstellt am 2012-06-19 13:44:08

Gerda

2012-06-19 13:44:08
  • #1
Hello,

we are building a house through a developer.
In the bathroom, we want to install the shower almost flush with the floor (flat shower tray, "recessed" in the screed).
According to the developer, the installation of sanitary fixtures + pipes should be done via a pre-wall installation.
A pre-wall behind the washbasin, the toilet, the bathtub, etc. makes sense to me.
But do all supply lines really have to be installed in a pre-wall? It should also be possible to lay the pipes (depending on the distance) in the screed.
I want to avoid having these unsightly "skirting boards" throughout the bathroom.
According to our developer, the pipes cannot be laid in the screed because underfloor heating is planned.
However, I have heard from other plumbing companies that precisely because underfloor heating is installed, the screed has a corresponding height and thus the pipes could be easily laid.
?!?
I don't have to lay the underfloor heating all the way to the "edge" of the room, do I? Are there certain norms, etc., that need to be observed here?
House is still in planning / construction of the shell has not yet started.
Unfortunately, the sanitary company has also not yet been decided.
 

Bauexperte

2012-06-20 12:53:10
  • #2
Hello,


Why don't you just build it flush with the floor - without a shower tray?


That is correct.


I don’t understand what you mean?


How does he want to create the necessary slope for the shower wastewater?


Under the bathroom, under all objects – including under the shower – or how should I understand this question?

Kind regards
 

Gerda

2012-06-22 11:48:05
  • #3
Question: In one corner of the room is the shower - flat shower tray, should be installed flush with the floor - then I have to bridge 2 meters along the wall to the shaft. Do I necessarily have to install a pre-wall between the shaft and the shower for the pipe installation? The screed is supposed to be about 14 cm "high" - as underfloor heating is planned. Second question: Can a pre-wall installation be executed only as high as the screed? The pipe cannot be positioned higher than the finished screed height, as I need the corresponding slope.
 

Bauexperte

2012-06-22 13:14:24
  • #4
Hello Gerda,


Everything I answer to you now can only be wrong => I am not a heating/plumbing specialist and do not know the exact floor construction; approximate figures are unfortunately not sufficient. Therefore, I would recommend that you get a second opinion from a sanitary installer and then discuss this information with your provider.

Kind regards
 

Similar topics
14.02.2015Floor-level shower drain with underfloor heating44
09.02.2015Floor-level shower with underfloor heating10
27.05.2016Plastic fittings/water pipes and insulating underfloor heating beneath screed?40
08.06.2016Questions about underfloor heating - new subfloor/screed/granite tiles14
11.01.2019Underfloor heating in the shower?14
15.12.2016Shower tray or tiled shower?24
29.03.2018Having underfloor heating milled in afterwards. Experiences!!!13
12.02.2017Water damage. Possibly a drilled underfloor heating?25
17.10.2017Additional bathroom through the builder or just laying pipes?10
27.12.2017Underfloor heating heating demand with at least 60 mm screed30
08.04.2018Is underfloor heating necessary in the shower? What do you think about it?35
07.10.2018Styrofoam under screed and underfloor heating - What is the name of the product?12
03.02.2019Underfloor heating in the floor slab - advantages and disadvantages?15
22.07.2019Drain pipe not under the screed37
01.02.2021Underfloor heating beneath bathtub and shower13
20.04.2021Shower slope in the wrong direction36
25.11.2022Mill underfloor heating or apply new screed?17
23.02.2024Retrofit bathtub or shower?27
20.04.2024Tiling in a level-floor shower34
02.10.2024Underfloor heating on the ground floor: insulate or not?16

Oben