Last week, excavation work for our house began... yesterday afternoon I received an email from my construction planner urgently requesting that I submit the base pipe layout from the building’s plumbing company by Monday morning (!!!). Since I have not yet met with the plumbing company about this matter, I am about 90% sure that it is not available? Especially since on Friday evening (when I read the email) I couldn’t reach anyone anymore...
What base pipes are even recorded there (and how)? In the construction start consultation, it was only determined where the connections for wastewater will go and how they will be led out of the house...
What base pipes are even recorded there (and how)? In the construction start consultation, it was only determined where the connections for wastewater will go and how they will be led out of the house...