Kollisionskurs
2013-03-12 09:13:41
- #1
Hello everyone,
we want to build a single-family house (passive house) in the near future and are currently in the exploratory phase.
The plot of land is available and the budget has an upper limit of €300,000.
First, we looked at and compared several prefab house providers (to get a feeling for the costs). Conclusion: overwhelmed by the multitude - everyone is of course the best quality on the market.
At the same time, we are considering building the house mostly ourselves stellen/bauen or there are several carpenters and other craftsmen in our family (I am the electrician, uncle is a painter, etc.). For this reason, we went to an architect to get a rough design and cost estimate if we design and have the house built in the traditional way at the drawing board.
He sketched a rough draft and listed the house turnkey in his preliminary cost estimate
(incl. outdoor facilities, garage).
The individual trades were not explicitly calculated, instead, a base value of €350 per m³ was assumed.
Thus, the total costs amount to approx. €420,000, which exceeds the budget.
The ancillary building costs were calculated at 15% of the total sum (architect, structural engineer, surveyor, building permit, soil expert, safety coordinator).
As far as I can assess, these figures are legitimate !?! – but in our case not affordable. As already mentioned, these are the costs for a house built by external companies - but we need the total for this house if we contribute a lot of own work. So we are considering having the architect finalize the drawings or create the plans. Only then can, for example, our carpenters prepare a calculation of material costs in advance, etc. This results in a price for each trade and in the end, we have our total costs including the "family" own contribution.
If the total costs decrease accordingly, the architect’s fee would also be smaller, right?
Because the fee is always based on the previously estimated construction costs.
Now, regardless of whether we ultimately reach our targeted budget and also that we would already have to pay the planning costs for the architect (without knowing exactly whether we can then build this house due to the resulting costs):
Do I have any other chance to calculate the costs in advance in our case?
How would the experienced proceed in our case? As mentioned, we are at the very beginning and therefore perhaps somewhat naive and often thinking differently... better now than later.
Grateful for any tips....
Best regards
we want to build a single-family house (passive house) in the near future and are currently in the exploratory phase.
The plot of land is available and the budget has an upper limit of €300,000.
First, we looked at and compared several prefab house providers (to get a feeling for the costs). Conclusion: overwhelmed by the multitude - everyone is of course the best quality on the market.
At the same time, we are considering building the house mostly ourselves stellen/bauen or there are several carpenters and other craftsmen in our family (I am the electrician, uncle is a painter, etc.). For this reason, we went to an architect to get a rough design and cost estimate if we design and have the house built in the traditional way at the drawing board.
He sketched a rough draft and listed the house turnkey in his preliminary cost estimate
(incl. outdoor facilities, garage).
The individual trades were not explicitly calculated, instead, a base value of €350 per m³ was assumed.
Thus, the total costs amount to approx. €420,000, which exceeds the budget.
The ancillary building costs were calculated at 15% of the total sum (architect, structural engineer, surveyor, building permit, soil expert, safety coordinator).
As far as I can assess, these figures are legitimate !?! – but in our case not affordable. As already mentioned, these are the costs for a house built by external companies - but we need the total for this house if we contribute a lot of own work. So we are considering having the architect finalize the drawings or create the plans. Only then can, for example, our carpenters prepare a calculation of material costs in advance, etc. This results in a price for each trade and in the end, we have our total costs including the "family" own contribution.
If the total costs decrease accordingly, the architect’s fee would also be smaller, right?
Because the fee is always based on the previously estimated construction costs.
Now, regardless of whether we ultimately reach our targeted budget and also that we would already have to pay the planning costs for the architect (without knowing exactly whether we can then build this house due to the resulting costs):
Do I have any other chance to calculate the costs in advance in our case?
How would the experienced proceed in our case? As mentioned, we are at the very beginning and therefore perhaps somewhat naive and often thinking differently... better now than later.
Grateful for any tips....
Best regards