NOmex
2017-06-11 10:05:10
- #1
Hello,
I hope you can help me with my question. We own a plot of land in a development area, which is currently being developed. The expected completion of the development is in August 2017. According to the municipality, once the development is completed, the development area will be finally surveyed and then an official site plan will be created by the surveying office (duration approx. 1-2 months).
According to the construction company, we also need this official site plan to submit the building documents for the building permit. This would mean that we can submit our building documents at the earliest in September/October.
However, I have now received from the municipality the statement that we should submit a so-called exemption application, since our house plan complies with the development plan and our house is thus an "exemption".
Does this now mean that with this exemption procedure we can already obtain a building permit without the official site plan?
I often see development areas being built on just days after the development, so there must already be a building permit in advance.
I hope I was able to convey our concern somewhat understandably. Thanks in advance for the answers.
I hope you can help me with my question. We own a plot of land in a development area, which is currently being developed. The expected completion of the development is in August 2017. According to the municipality, once the development is completed, the development area will be finally surveyed and then an official site plan will be created by the surveying office (duration approx. 1-2 months).
According to the construction company, we also need this official site plan to submit the building documents for the building permit. This would mean that we can submit our building documents at the earliest in September/October.
However, I have now received from the municipality the statement that we should submit a so-called exemption application, since our house plan complies with the development plan and our house is thus an "exemption".
Does this now mean that with this exemption procedure we can already obtain a building permit without the official site plan?
I often see development areas being built on just days after the development, so there must already be a building permit in advance.
I hope I was able to convey our concern somewhat understandably. Thanks in advance for the answers.