Building drying: Is it better to turn off the controlled residential ventilation system in summer?

  • Erstellt am 2017-05-12 17:29:51

Barossi

2017-05-12 17:29:51
  • #1
Hello,

we want to dry our construction before moving in, and the screed is not yet ready for covering (CM:2.3).

We have 2 large construction dryers in operation. Should the already installed controlled residential ventilation system (Zehnder Q450) be turned off or run at maximum during the current temperatures? (Currently just under 20°C and about 80-90% humidity)

Or is it better to run it at maximum only in the evening/night when the air is cooler (at night around 10°C)?

Best regards, Barossi
 

Knallkörper

2017-05-12 19:04:28
  • #2
I think that regarding dehumidification, it doesn’t matter at all whether your [Kontrollierte-Wohnraumlüftung] is running. At the level you are operating (30%), hardly any water is extracted from the air. Whatever still needs to be done, your building dryers can easily handle. If your humidity varies greatly from room to room, the [Kontrollierte-Wohnraumlüftung] could be turned on for circulation purposes; otherwise, I would turn it off, save energy, and enjoy the still clean filters.
 

Alex85

2017-05-12 19:09:55
  • #3
I thought the controlled residential ventilation should only be switched on after the building drying, due to contamination and initially continuously humid air in the system ... this was already discussed somewhere.
 

Barossi

2017-05-12 19:26:04
  • #4
Well, the house is no longer really damp, the screed is still acting up (CM: 2.3), and I wanted to support the dehumidifiers a bit with the [Kontrollierte-Wohnraumlüftung]. What else should happen except replacing filters due to dust. I just read that in summer the [Kontrollierte-Wohnraumlüftung] additionally brings moist air into the house.
 

Alex85

2017-05-12 19:34:26
  • #5
I would not want construction dust in the piping system or even the heat exchanger. Take a look at the manual, there might already be a warranty exclusion there. I would at least cover all exhaust air vents separately with filter mats. Depending on the amount of dust, these would need to be changed very regularly.
 

Barossi

2017-05-12 19:50:27
  • #6
I'm not worried about that, the work is completed, the floor has been vacuumed. We are only waiting for the drying of the screed. No more dust is generated. I wanted to supplement the dehumidifiers with the [Kontrollierte-Wohnraumlüftung].
 

Similar topics
01.08.2014Water-bearing wood stove (supplement to the air-water heat pump and controlled residential ventilation with heat recovery)?10
22.09.2016Offer KfW70 house - KfW55 house already with additional controlled residential ventilation - Is KfW70 too airtight?12
29.04.2018Gas heating + solar & controlled residential ventilation or air-water heat pump Energy Saving Ordinance 201626
04.09.2018Pantry: Is a heating coil sensible in controlled residential ventilation?14
01.02.2019Controlled residential ventilation with cooling: brine geothermal heat pump instead of air-to-water heat pump?30
25.02.2022Too much moisture in the single-family house after screed installation? Risk of mold?49

Oben