Hello,

our main contractor would like to have a financing confirmation from us or an assignment of the last 6 installment payments. Something like this:

The purchase contract amount is financed by the "bank". The client hereby assigns the installments (last 6) according to the payment schedule totaling x € of the main contractor contract to "the construction company". The release is made by the client and is paid to "the construction company" within the assigned claim and in accordance with the conditions of the contract upon presentation of the invoice.

Do I then really have control over the last payments?

Regards.
 

HilfeHilfe

2018-06-19 12:08:58
  • #2
Unusual. Normally, one calls off, the bank also charges for that, and then the GU calls off independently. It gets exciting when you sign it and in the end there are discrepancies. You have it fixed elsewhere, the GU insists on the payment obligation.
 

Rumpelkopf

2018-06-19 16:08:48
  • #3
I suspect that the bank will not comply with the assignment at all. You retain control because you have to authorize the release of the payment. In principle, the bank only wants to prevent the builder from having the money transferred to their account and, for example, withholding the final installment while already having the money in the account. Which bank was financing?
 

HilfeHilfe

2018-06-19 16:21:56
  • #4
Please read the post again, think about it! And then reply! The general contractor wants the assignment, not the bank!
 

Rumpelkopf

2018-06-19 18:23:16
  • #5


Exactly, HilfeHilfe, and the bank will not agree to the assignment.

What is there to complain about and think about again?
 

Knallkörper

2018-06-19 18:53:10
  • #6
Don't do that. If you want to withhold a partial payment completely or partially because of defects, it will certainly get complicated.

Withholding money because of defects is your sharpest weapon.
 

Similar topics
26.12.2012Prefabricated house / solid house, which construction companies?16
17.02.2016Architect or construction company?23
06.10.2016No groundbreaking yet, but already trouble with the construction company28
22.08.2017Connection between financial intermediary and construction company14
15.09.2023Heilbronn surrounding area - experiences with local construction companies26
20.03.2020Construction company halts work despite overpayment718
30.04.2020Construction company with "land service"43
18.08.2020Experiences with construction companies in Berlin and surrounding areas (approx. 50 km)86
12.01.2024Construction company insolvent, how to proceed further?34
05.02.2025Providers of credit reports on construction companies?10

Oben