What struck me when reading through for the first time,
- Civil engineering works are completely missing (drainage, excavation, transport, landfill)
- You probably have to accept costs for construction electricity/water and surveying. I’m not paying anything. For me, it all falls under site setup for €1500. Of course, I have to pay for water/electricity. Was the toilet included?
- Ceiling for central ventilation, if desired, should be 22 cm
- You will pay a surcharge for tiles everywhere. Both for the tiles and for the installation.
- I only know lime cement plaster in the bathrooms. It should rather be lime gypsum plaster. Have you ever seen an unpapered wall? That’s what it will look like with lime cement plaster.
- Nothing can be said about electrical/windows/doors/heating. It can be junk or brand name.
- Where is the soil investigation and ground analysis?
- Otherwise, all prices are a bit higher than with my individual trade contracts.
EDIT: Don’t take the scaffolding issue lightly. You need it once for the shell construction + roof and for the clinker. Depending on duration, that easily starts at €3.5k upwards.
What about drainage? Are you doing that?