Hello everyone,
my wife and I are currently in the early stages of planning our single-family house in Lower Saxony, which should have a floor area of about 170 sqm without a basement. To be able to first see what is feasible with our budget, I would like to realistically estimate the ancillary costs from the start. For this, I now need your help. I will simply list what I have planned so far and how expensive it will (or could) be and ask you to help me identify where my estimate is completely unrealistic or if I have forgotten something. We will not need an architect.
Ancillary construction costs in euros:
Plot incl. all ancillary costs: 58000
Surveying/cadastre: 2600
Soil report: 600
If necessary, plot clearance: 200
Building permit: 800
Review of construction contract: 500
Construction water/electricity incl. consumption: 1000
If necessary, earthworks (buffer): 2000
Development (electricity, water, gas): 7000
Insurances: 500
Construction period interest: 2000
Building expert: 2000
Outdoor facilities: 10000 - x ?
Carport/garage: 15000 - x ?
Kitchen: 10000 - 20000
Floor coverings and painting: 15000
Have I forgotten something or allocated significantly too much somewhere? Some positions like the kitchen etc. are of course very individual
Thanks in advance
my wife and I are currently in the early stages of planning our single-family house in Lower Saxony, which should have a floor area of about 170 sqm without a basement. To be able to first see what is feasible with our budget, I would like to realistically estimate the ancillary costs from the start. For this, I now need your help. I will simply list what I have planned so far and how expensive it will (or could) be and ask you to help me identify where my estimate is completely unrealistic or if I have forgotten something. We will not need an architect.
Ancillary construction costs in euros:
Plot incl. all ancillary costs: 58000
Surveying/cadastre: 2600
Soil report: 600
If necessary, plot clearance: 200
Building permit: 800
Review of construction contract: 500
Construction water/electricity incl. consumption: 1000
If necessary, earthworks (buffer): 2000
Development (electricity, water, gas): 7000
Insurances: 500
Construction period interest: 2000
Building expert: 2000
Outdoor facilities: 10000 - x ?
Carport/garage: 15000 - x ?
Kitchen: 10000 - 20000
Floor coverings and painting: 15000
Have I forgotten something or allocated significantly too much somewhere? Some positions like the kitchen etc. are of course very individual
Thanks in advance